Question

Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...

  • Refer to the information below:

Depends On

Optimistic Duration(days)

Most Likely Duration(days)

Pessimistic Duration(days)

A

-

7

10

18

B

A

3

8

14

C

B

10

14

22

D

A

2

5

9

E

B,D

7

9

15

F

C,D

4

9

19

G

B

10

15

29

H

C,E,F

2

8

19

I

G,H

1

2

7

J

I

3

9

18

  • Determine the following for each activity:
    • Expected Duration (round to the nearest whole number)
    • Early Start (ES)
    • Early Finish (EF)
    • Late Start (LS)
    • Late Finish (LF)
    • Total Float (TF)
    • Variance
  • Determine the following for the project:
    • Critical Path (CP)
    • Number of Days required to complete the project (i.e., Expected Project Duration)
  • Determine the probability that the project will complete in 76 days or less.
  • Determine the probability that the project will complete in 58 days or less.

Please complete in excel and include formulas used.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration Weighted duration Immediate Predecessor P 15 27 21 - Q 18 36 24 P R 26 40 24 P S 21 39 27 Q T 27 33 24 Q,R U 16 32 24 S,T V 16 30 26 U 1. Calculate the actual duration of each activity (fill-in the table) 2. Draw an AOA network diagram for the activities (in the space below): 3....
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Assume that activity F has the following times: Early start time (ES) = 7 days Early...
Assume that activity F has the following times: Early start time (ES) = 7 days Early finish time (EF) = 13 days Latest start time (LS) = 15 days Latest finish time (LF) = 21 days Which of the following statements is TRUE about activity F? Activity F takes 14 days to complete Activity F is on the critical path Activity F has 8 days of slack time Activity F is the first activity of the project None of the...
Use the table below to answer the questions 25 to 28. Activity Optimistic duration Pessimistic duration...
Use the table below to answer the questions 25 to 28. Activity Optimistic duration Pessimistic duration Most Likely duration Weighted duration Immediate Predecessor P 15 27 21 - Q 18 36 24 P R 26 40 24 P S 21 39 27 Q T 27 33 24 Q,R U 16 32 24 S,T V 16 30 26 U Calculate the actual duration of each activity (fill-in the table) Draw an AOA network diagram for the activities (in the space below):...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT