Mr. King performed logistic regression for his manufacturing project. The actual observed odd ratio for his project is 3/2. However, his predicted odds ratio is 2/3. Please help Mr. King to calculate the absolute difference between observed probability and estimated/predicted probability.
Odds ratio = Probability of event / Probability of non-events
Probability of non-events = 1 - Probabiloty of events
So odds ratio = Probability of event / ( 1 - Porbability of events)
Given our observed odds ratio = 3/2
Let the obersved probability be Po
So 3/2 = Po / 1 - Po
3 * ( 1 - Po) = 2 * Po
3 - 3Po = 2Po
5Po = 3
So Po = 3/5
The obersved probability be 3/5
Given our predicted (estimated) odds ratio = 2/3
Let the predicted or estimated probability be Pe
So 2/3 = Pe / 1 - Pe
2 * ( 1 - Pe) = 3 * Pe
2 - 2Pe = 3Pe
5Pe = 2
So Pe = 2/5
The predicted or estimared probability be 2/5
The difference between observed probability (Po) and estimated/predicted probability (Pe) = 3/5 -2/5 = 1/5
The difference between observed probability (Po) and estimated/predicted probability (Pe) is 1/5