Problem #5 An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity.
Activity |
Expected time (weeks) |
Budgeted Cost |
Immediate Predecessors |
A |
3 |
$2,000 |
None |
B |
4 |
$6,000 |
None |
C |
2 |
$7,000 |
A |
D |
5 |
$9,000 |
B |
E |
3 |
$3,000 |
C |
F |
6 |
$8,000 |
B,D |
Develop a budget for the 15 weeks of the project using LS times.
ANSWER:
Given that,
Total price of the project would be sum of all the budgeted cost = $2000+ $ 6000 + $ 7000 + $9000 + $3000 + $8000
= $ 35000
Day | As per ES |
Day 1 | 2166.6667 |
Day 2 | 2166.6667 |
Day 3 | 2166.667 |
Day 4 | 5000 |
Day 5 | 5300 |
Day 6 | 2800 |
Day 7 | 2800 |
Day 8 | 2800 |
Day 9 | 1800 |
Day 10 | 1333.333 |
Day 11 | 1333.333 |
Day 12 | 1333.333 |
Day 13 | 1333.333 |
Day 14 | 1333.333 |
Day 15 | 1333.333 |
Get Answers For Free
Most questions answered within 1 hours.