A microwave manufacturing company has just switched to a new automated production system. Unfortunately, the new machinery has been frequently failing and requiring repairs and service. The company has been able to provide its customers with a completion time of 6 days or less. To analyze whether the completion time has increased, the production manager took a sample of 25 jobs and found that the sample mean completion time was 6.5 days with a sample standard deviation of 1.5 days. At significance levels of .05, test whether the completion time has increased. (construct the hypotheses, show the critical and calculated values of the test statistic and perform test)

Homework Answers

Answer #1

H0: <= 6

Ha: > 6

Test statistics

t = - / S / sqrt(n)

= 6.5 - 6 / 1.5 / sqrt(25)

= 1.67

This is test statistics value.

Critical value at 0.05 level with 24 df = 2.492

Since test statistics falls in non-rejection region, we do not have sufficient evidence to reject H0.

We conclude at 0.05 level that we fail to support the claim.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
10) A microwave manufacturing company has just switched to a new automated production system. Unfortunately, the...
10) A microwave manufacturing company has just switched to a new automated production system. Unfortunately, the new machinery has been frequently failing and requiring repairs and service. The company has been able to provide its customers with a completion time of 6 days or less. To analyze whether the completion time has increased, the production manager took a sample of 25 jobs and found that the sample mean completion time was 6.5 days with a sample standard deviation of 1.5...
A microwave manufacturing company has just switched to a new automated production system. Unfortunately, the new...
A microwave manufacturing company has just switched to a new automated production system. Unfortunately, the new machinery has been frequently failing and requiring repairs and service. Historically, the company has been able to provide its customers with a completion time of 6 days or less. To analyze whether the completion time has increased, the production manager took a sample of 36 jobs and found that the sample mean completion time was 6.5 days with a sample standard deviation of 1.5...
Data Screen Corporation is a highly automated manufacturing firm. The vice president of finance has decided...
Data Screen Corporation is a highly automated manufacturing firm. The vice president of finance has decided that traditional standards are inappropriate for performance measures in an automated environment. Labor is insignificant in terms of the total cost of production and tends to be fixed, material quality is considered more important than minimizing material cost, and customer satisfaction is the number one priority. As a result, production and delivery performance measures have been chosen to evaluate performance. The following information is...
Wolk Corporation is a highly automated manufacturing firm. The vice president of finance has decided that...
Wolk Corporation is a highly automated manufacturing firm. The vice president of finance has decided that traditional standards are inappropriate for performance measures in an automated environment. Labor for this company is insignificant in terms of the total cost of production and tends to be fixed, material quality is considered more important than minimizing material cost, and customer satisfaction is the number one priority. As a result, delivery performance measures have been chosen to evaluate performance. The following information is...
) A company has just switched to a 4-day work week. It has measured the number...
) A company has just switched to a 4-day work week. It has measured the number of units produced per week for 10 employees before and after the change. Does the change impact production. Employee Before After A 25 23 B 26 24 C 27 26 D 22 19 E 29 30 F 25 24 G 29 22 H 30 32 I 25 23 J 28 21 Does changing the workweek influence sales? Use α =.05 2 tailed. State the...
Burrito King (a new fast-food franchise opening up nationwide) has successfully automated burrito production for its...
Burrito King (a new fast-food franchise opening up nationwide) has successfully automated burrito production for its drive-up fast-food establishments. The Burro-Master 9000 requires a constant 30 seconds to produce a batch of burritos. It has been estimated that customers will arrive at the drive-up window according to a Poisson distribution at an average of one every 55 seconds. To help determine the amount of space needed for the line at the drive-up window, answer the following questions. a. What is...
(12 marks) Jody has just begun a new job with a production company. He will work...
Jody has just begun a new job with a production company. He will work 40- hour weeks and each month various measures of his performance are checked. In his first month (4 weeks) Jody produced 500 units; in his second month (5 weeks) he produced 725 units. Calculate Jody’s productivity for each month and indicate whether his productivity has grown or declined.
Burrito King (a new fast-food franchise opening up nationwide) has successfully automated burrito production for its...
Burrito King (a new fast-food franchise opening up nationwide) has successfully automated burrito production for its drive-up fast-food establishments. The Burro-Master 9000 requires a constant 45 seconds to produce a batch of burritos. It has been estimated that customers will arrive at the drive-up window according to a Poisson distribution at an average of one every 48 seconds. To help determine the amount of space needed for the line at the drive-up window, answer the following questions. a. What is...
The production manager, Christina, of WidgetsCo Production has just been approached with an exciting new opportunity...
The production manager, Christina, of WidgetsCo Production has just been approached with an exciting new opportunity by the marketing manager of the company. The marketing manager has given Christina some information and has asked her to determine whether this is a feasible opportunity. If so, what should the sales and marketing targets be for the company? The marketing manager and Christina have had their differences in the past when the company undertook ventures without consulting production. This caused remarkable problems,...
A new operating system is installed in every workstation at a large company. The claim of...
A new operating system is installed in every workstation at a large company. The claim of the operating system manufacturer is that the time to shut down and turn on the machine will be much faster. To test it an employee selects 32 machines and tests the combined shut down and restart time of each machine before and after the new operating system has been installed. The mean of the differences ​(beforeminus​after) is 23.4 seconds with a standard deviation of...