13. What is "Lean Manufacturing"? a) A metal product used in the electronics industry b) A way for companies to rid of much waste that adds no value to production c) The preferred vendor to a company d) A holiday
14. In project management, the scheduling function: a. is probably the major tool for the management of projects. b. is so important that a detailed schedule is sometimes a customer-specified requirement. c. can serve as a key input in the establishment of the monitoring and control system.
15. Which of the following is NOT true about the Student’s t distribution? a. It has more areas in the tails and less in the center than does the normal distribution. b. It is used to construct confidence intervals for the population mean when the population standard deviation is known. c. It is bell shaped and symmetrical. d. As the number of degrees increases, the t distribution approaches the normal distribution.
16. A graphical tool often used to help identify opportunities for improvement is: a. ANOVA b. Cost/benefit analysis c. Pareto Analysis d. Control Charts
17. The binomial distribution is a discrete distribution and may be used to describe: a) sampling without replacement from a finite population b) The case of n independent trials with probabilities constant from trial to trial. c) The case of n independent trials with several outcomes for each trial d) Sampling without replacement from a finite population where there are several outcomes for each trial
18. Lean enterprise may be summarized as: a) An entire organization involved with improvement b) Implementation of SMED cycle time techniques c) Poka-yoke techniques in action d) Ergonomic principles in the workplace
Answer 13
Lean manufacturing is defined as the process in which the waste is removed from the manufacturing and making the manufacturing process more efficient.
Removing the waste from the manufacturing process also results in increased profit for the manufacturer.
So, only option B is correctly defining the lean manufacturing.
Option B is correct answer
Answer 14
Option A is correct because the scheduling function is used to assign and prioritise tasks in the project management based on their time completion. Scheduling function makes efficient use of all the equipment given for the task completion, thus we can say that it is a major tool for the management of projects.
Answer 15
We know that when we have population standard deviation, i.e. when the population standard deviation is known, we use z distribution and when the population standard deviation is unknown, we use t distribution.
So, option C is incorrect about the t distribution because when the population standard deviation is known, then we use z distribution and not t distribution for calculation of confidence interval.
Get Answers For Free