Question

Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity,...

Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows:

Supplier
Component 1 2 3
1 $10 $14 $13
2 $12 $12 $12

Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as Edwards provides sufficient advance orders, each supplier can devote its capacity to component 1, component 2, or any combination of the two components, if the total number of units ordered is within its capacity. Supplier capacities are as follows:

Supplier 1 2 3
Capacity 550 1025 800

If the Edwards production plan for the next period includes 1050 units of component 1 and 800 units of component 2, what purchases do you recommend? That is, how many units of each component should be ordered from each supplier?

Supplier
1 2 3
Component 1
Component 2

What is the total purchase cost for the components?

$  

Homework Answers

Answer #1

applying given constraint and using excel solver:

Order quantity:
Component 1 2 3 total qty constraint total
1 550 0 500 1050 = 1050
2 0 501 299 800 = 800
550 501 799
constraint <= 550 1025 800
slack 0 524 1
total cost = 21600

from above:

1)

Supplier:
Component 1 2 3
1 550 0 500
2 0 501 299

2)

total purchase cost for the components =21600

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity,...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $12 $14 $10 2 $14 $12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity,...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $12 $13 $10 2 $11 $12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity,...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $12 $14 $10 2 $14 $12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity,...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $12 $13 $10 2 $15 $12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as...
Problem 9-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers...
Problem 9-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $11 $11 $13 2 $10 $12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However,...
Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers...
Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $11 $12 $15 2 $11 $14 $11 Each supplier has a limited capacity in terms of the total number of components it can supply. However,...
Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in...
Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment is as follows.   Supplier Component A B C Defective 10 30...
Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in...
Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion of defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment are as follows. Component Supplier A B C Defective 15...
In the automotive industry there are three types of suppliers ranging from parts and components suppliers...
In the automotive industry there are three types of suppliers ranging from parts and components suppliers to systems and modules suppliers. The supply chain works as follows: Parts Suppliers (Tier 3) >> Components Suppliers (Tier 2) >> Systems and Components Suppliers (Tier 1)  >> OEM (Assembly Plant) Tier 1 is a supplier that ships directly to the Assembly plant properly and strictly sequenced (Just In Time). Sequencing depend of the actual current demand. Tier 1’s goods are received and assembled straight...
Grand Limited currently produces a component of a product with the following per unit production costs:...
Grand Limited currently produces a component of a product with the following per unit production costs: Direct materials $18 Direct labour 31 Overhead 18 Total production costs $67 Grand Ltd. currently manufactures these components in-house, averaging production of 29020 units each year. A supplier has approached the company offering to supply 29020 units each year at a cost of $48 each. 60% of the overhead is fixed and if Grand Ltd. purchases the components, then 1/3 of the fixed overhead...