Question

1. Using the data below, what is the value of RMSE? Week Time Series Value Forecast...

1.

Using the data below, what is the value of RMSE?

Week

Time Series Value

Forecast

1

3

7.00

2

5

4.00

3

2

5.00

4

8

8.00

2.

Using the data below, calculate the squared error for the 4th week. Use the 2 period moving average to create the forecast.

Week

Time Series Value

1

19.00

2

11.00

3

22.00

4

7.00

Please, do the all the work and show processes

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 14...
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 14 16 12 17 14 Using the naive method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. Round the intermediate calculations to two decimal places. Mean absolute error (to 1 decimal). Mean squared error (to 1 decimal). Mean absolute percentage error (to 2 decimals). % What is the forecast for week 7 (to the nearest whole...
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 13...
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 13 16 11 17 14 A) What type of pattern exists in the data? (HORIZONTAL OR TREND) B) Develop a three-week moving average for this time series. Compute MSE and a forecast for week 7. If required, round your answers to two decimal places. Week Time Series Value Forecast 1 18 2 13 3 16 4 11 _______ 5 17 _______ 6 14 _______ MSE:...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 12...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 12 16 11 18 13 (b) Develop the three-week moving average forecasts for this time series. (Round your answers to two decimal places.) Week Time Series Value Forecast 1 19 2 12 3 16 4 11 5 18 6 13 Compute MSE. (Round your answer to two decimal places.) MSE =   What is the forecast for week 7? (c) Use α = 0.2 to compute...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14 16 11 18 15 Using the naive method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. Round the intermediate calculations to two decimal places. Mean absolute error (to 1 decimal). Mean squared error (to 1 decimal). Mean absolute percentage error (to 2 decimals). % What is the forecast for week 7 (to the nearest whole...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14 17 10 17 13 Using the naive method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. (a) mean absolute error MAE = (b) mean squared error MSE = (c) mean absolute percentage error (Round your answer to two decimal places.) MAPE = % (d) What is the forecast for week 7?
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 12...
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 12 17 11 17 14 Using the naive method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. (a) mean absolute error MAE = (b) mean squared error MSE = (c) mean absolute percentage error (Round your answer to two decimal places.) MAPE = % (d) What is the forecast for week 7?
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 13...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 13 16 11 17 15 Using the average of all the historical data as a forecast for the next period, compute the following measures of forecast accuracy. Round your answers to two decimal places. a. Mean absolute error. b. Mean squared error. c. Mean absolute percentage error. % d. What is the forecast for week 7?
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14 17 12 18 15 Using the average of all the historical data as a forecast for the next period, compute the following measures of forecast accuracy. Round your answers to two decimal places. a. Mean absolute error. b. Mean squared error. c. Mean absolute percentage error. d. What is the forecast for week ?
Consider the following time series data. Week 1 2 3 4 5 6 Value 20 12...
Consider the following time series data. Week 1 2 3 4 5 6 Value 20 12 15 11 19 15 Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. Mean absolute error. Round your answer to one decimal place. ________ Mean squared error. Round your answer to one decimal place. _______ Mean absolute percentage error. Round your answer to two decimal places. _______ What is the forecast for...
Consider the following time series data. Week 1 2 3 4 5 6 Value 20 12...
Consider the following time series data. Week 1 2 3 4 5 6 Value 20 12 15 10 19 14 Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. Mean absolute error. Round your answer to one decimal place. Mean squared error. Round your answer to one decimal place. Mean absolute percentage error. Round your answer to two decimal places. What is the forecast for week 7? Round...