Freight car loadings over a 10-week period at a busy port are as follows:
Week |
Number |
1 |
220 |
2 |
245 |
3 |
280 |
4 |
275 |
5 |
300 |
6 |
310 |
7 |
362 |
8 |
360 |
9 |
402 |
10 |
400 |
Develop forecast from week 5 to week 10 by using 4-week moving average.
Find the MAD for this forecasting method.
Please round your answer to 4 decimal places if necessary.
The 4-month moving average forecasts are calculated in the table below:
Week | Number(A) | Forecasts(F) | Absolute Error =|A-F| |
1 | 220 | - | - |
2 | 245 | - | - |
3 | 280 | - | - |
4 | 275 | - | - |
5 | 300 | (220 + 245 + 280 + 275)/4 = 255 | |300-255| = 45 |
6 | 310 | (245 + 280 + 275 + 300)/4 = 275 | |310-275| = 35 |
7 | 362 | (280 + 275 + 300 + 310)/4 = 291.25 | |362-291.25| = 70.75 |
8 | 260 | (275 + 300 + 310 + 362)/4 = 311.75 | |260-311.75| = 51.75 |
9 | 402 | (300 + 310 + 362 + 260)/4 = 308 | |402-308| = 94 |
10 | 400 | (310 + 362 + 260 + 402)/4 = 333.5 | |400-333.5| = 66.5 |
Total | - | - | 363 |
-------------------------------------------------------------------------------