A new process is started, and the sum of the sample standard deviation, ∑s, for 25 rows of measurement, each of subgroup size 4, is 750. If the specifications are 700 ± 80 and the process center, Xbar-bar = 720, compute (to 3 decimal places) the Process Capability Index Cpk. (Please show all work)
Cpl = (Mean – LSL)/3*
Cpu = (USL – Mean)/3*
Process Capability Index Cpk = Min (Cpl, Cpu)
LSL = 700 - 80 = 620
USL = 700 + 80 = 780
Mean – LSL = 720 - 620 = 100
USL – Mean = 780 - 720 = 60
Thus,
Process Capability Index Cpk = 60 / 3*
Process standard deviation, = / c4
= / 25 = 750 / 25 = 30
c4 for subgroup size 4 is 0.9213
Process standard deviation, = 30 / 0.9213 = 32.56268
Process Capability Index Cpk = 60 / (3*32.56268) = 0.614