Question

If the following jobs are sequenced according to the SLACK rule then job A would be...

If the following jobs are sequenced according to the SLACK rule then job A would be completed on day (assume zero for today's date)

Job - Processing Time (days) - Due Date

A 8 12

B 6 15

C 11 17

D 7 10

E 3 8

Select one: A. 7. B. 15. C. 8. D. 12.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job A, Process time =14 days, and due date November 26 Job B, Process time= 11 days, and due date = November 25 Job C, Process time =7 days, and due date= December 14 Job D, Process time=6 days, and due date= November 29 Job E, Process time= 2 days, and due date= November 20 Schedule the jobs according to SPT. What are the average...
Five jobs are ready for processing at time zero through a workstation. The details of the...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
You have the following information on four jobs. Today is the beginning of day 1, so...
You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining. Job Time Needed (days) Due (days) P 8 8 Q 10 23 R 3 17 S 6 30 T 4 29 U 7 24 1. If you order these jobs by Shortest Process Time rule, the order will be: 2. If you order these jobs by Earliest Due...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
The scheduling rule that minimizes the makespan time for a set of jobs that must be...
The scheduling rule that minimizes the makespan time for a set of jobs that must be processed through a two-step system where every job follows the same sequence through the two processes is A. the shortest processing time (SPT). B. Johnson’s Rule. C. the assignment method. D. the minimal slack rule.
What is the optimum job sequence for the jobs listed below using Johnson's Rule? Processing time(hrs)...
What is the optimum job sequence for the jobs listed below using Johnson's Rule? Processing time(hrs) Job Center 1 Center 2 d 13 23 e 23 14 f 16 18 g 20 17 A. e-g-f-d B. d-g-f-e C. d-f-g-e D. e-d-f-g E. f-e-d-g
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule. Job Due Date Remaining Time (Days) A 212 6 B 209 3 C 214 10 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum lateness?
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Processing Due Job Time (days) Date (Days) W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A. 0 B. 1 C. 2 D. 3 E. 4