Question

Your project has a budget of $290,000 and is 30 percent complete. You have spent $90,000...

Your project has a budget of $290,000 and is 30 percent complete. You have spent $90,000 on your project, however due to some rework and additional time from a vendor. Your project is supposed to be 50 percent complete by this time. What is your estimate to complete (ETC) for this project?

Homework Answers

Answer #1

Sol:

Find the Estimate to Complete (ETC) for this project.

Given in the question:

Budget at Completion (BAC) = $290,000

Actual Cost (AC) = $90,000

Planned Value (PV) = 50% of $290,000

= $145,000

Earned Value (EV) = 30% of $290,000

= $87,000

To determine the ETC, you need the EAC.

And, EAC = BAC / CPI

Hence, Cost Performance Index (CPI) = EV / AC

= $87,000 / $90,000

CPI = 0.9667

Therefore,

Cost Performance Index (CPI) = 0.9667

Now, Estimate at Completion (EAC) = BAC / CPI

= $290,000 / 0.9667

= $299989.656

EAC = $299,990 (approx)

Estimate at Completion (EAC) = $299,990

Now, Estimate to Complete (ETC) = EAC – AC

= $299,990 – $90,000

ETC = $209,990

Hence,

The Estimate to Complete (ETC) for this project is $209,990

If you Satisfy with Answer, Please give me "Thumb Up". It was very important to me.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
9. You have spent $12,500 on a project so far. The project is behind schedule and...
9. You have spent $12,500 on a project so far. The project is behind schedule and over budget so the PMO is considering abandoning the project. The original estimate for project costs was $10,000 and the NPV of the 5 year project was expected to be $5,000. What is the sunk cost of the project? (3 points) Give three examples of sunk costs which could occur on a project. (3 points)
With the following information, complete a time-phased budget for your project. What are the weekly and...
With the following information, complete a time-phased budget for your project. What are the weekly and cumulative costs? TASK Budget Week 1 Week 2 Week 3 Week 4 Week 5 A 9 7 2 B 16 4 10 2 C 17 2 10 4 1 D 30 4 12 14 Plan Cumulative
Your project has a total budget of $10,000,000. At the end of week 26 of your...
Your project has a total budget of $10,000,000. At the end of week 26 of your project, you have the following values: Planned Value: $1,000,000 Earned Value: $750,000 Actual Cost: $1,250,000 Questions: What is your schedule variance? Is your project ahead of or behind schedule? What is your cost variance? Is your project over budget or under budget? Provide two estimates of the cost at completion for your project. Be sure to show your calculations.
You have been told that your organization will accept a project that has a payback of...
You have been told that your organization will accept a project that has a payback of 3 years or less. You have $100 to invest, and you can accept either Project A or Project B. According to your decision criteria, which project should be chosen? What are the problems with this analysis and the decision? Project A:  NINV = –100: NCF1 = 20 : NCF2 = 30: NCF3 = 50 Project B: NINV = –100: NCF1 = 20: NCF2 = 30:...
You plan to purchase a house for $290,000 using a 30-year mortgage obtained from your local...
You plan to purchase a house for $290,000 using a 30-year mortgage obtained from your local bank. You will make a down payment of 20 percent of the purchase price. You will not pay off the mortgage early. Assume the homeowner will remain in the house for the full term and ignore taxes in your analysis. Your bank offers you the following two options for payment. Option 1: Mortgage rate of 6.50 percent and zero points. Option 2: Mortgage rate...
You have examined the budget reports and have discovered that in the first quarter reporting, one...
You have examined the budget reports and have discovered that in the first quarter reporting, one section has spent over 75% of their budget allocation. What will you do and should you be concerned about this? Discuss in 50 to 80 words. (Please answer in Australian Accounting Environment and please type up your answer)
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent Completed A 3.00 - 15000 1.00 B 1.00 A 5000 0.00 C 2.00 A 10000 1.00 D 3.00 A 21000 0.50 E 2.00 B,C 32000 0.00 F 1.00 C 5000 0.00 G 1.00 C 5500 0.00 The project started on June 1st. The project has a planned duration of 7 months. Data below are planned cost and actual cost (spent) from June to November:...
You have invested 30 percent of your portfolio in Jacob, Inc., 40 percent in Bella Co.,...
You have invested 30 percent of your portfolio in Jacob, Inc., 40 percent in Bella Co., and 30 percent in Edward Resources. What is the expected return of your portfolio if Jacob, Bella, and Edward have expected returns of 0.06,0.20, and 0.14, respectfully?
.Why is your knowledge of Risk appetite and Risk threshold important in your Risk response strategy?...
.Why is your knowledge of Risk appetite and Risk threshold important in your Risk response strategy? 2.You had planned in your risk response to engage two additional programmers during the implementation stage of your project. Suddenly you realized that you may need a total of three. What are three possible things that you must do to ensure that the project is not delayed? 3.You are the project manager of a software development company. Your company receives supplies of chips from...
Group Assignment: 1.Why is your knowledge of Risk appetite and Risk threshold important in your Risk...
Group Assignment: 1.Why is your knowledge of Risk appetite and Risk threshold important in your Risk response strategy? 2.You had planned in your risk response to engage two additional programmers during the implementation stage of your project. Suddenly you realized that you may need a total of three. What are three possible things that you must do to ensure that the project is not delayed? 3.You are the project manager of a software development company. Your company receives supplies of...