Your project has a budget of $290,000 and is 30 percent complete. You have spent $90,000 on your project, however due to some rework and additional time from a vendor. Your project is supposed to be 50 percent complete by this time. What is your estimate to complete (ETC) for this project?
Sol:
Find the Estimate to Complete (ETC) for this project.
Given in the question:
Budget at Completion (BAC) = $290,000
Actual Cost (AC) = $90,000
Planned Value (PV) = 50% of $290,000
= $145,000
Earned Value (EV) = 30% of $290,000
= $87,000
To determine the ETC, you need the EAC.
And, EAC = BAC / CPI
Hence, Cost Performance Index (CPI) = EV / AC
= $87,000 / $90,000
CPI = 0.9667
Therefore,
Cost Performance Index (CPI) = 0.9667
Now, Estimate at Completion (EAC) = BAC / CPI
= $290,000 / 0.9667
= $299989.656
EAC = $299,990 (approx)
Estimate at Completion (EAC) = $299,990
Now, Estimate to Complete (ETC) = EAC – AC
= $299,990 – $90,000
ETC = $209,990
Hence,
The Estimate to Complete (ETC) for this project is $209,990
If you Satisfy with Answer, Please give me "Thumb Up". It was very important to me.
Get Answers For Free
Most questions answered within 1 hours.