Question

Remington Textiles has a mill that produces three types of fabrics on a make-to-order basis. The...

Remington Textiles has a mill that produces three types of fabrics on a make-to-order basis. The mill operates on a 24/7 basis. The key decision facing the plant manager is about the type of loom needed to process each fabric during the coming 12 weeks to meet demands for the three fabrics and not exceed the capacity of the looms in the mill. Two types of looms are used: Jaquard and Northrop. Jaquard looms can be used to make all fabrics and are the only looms that can weave certain fabrics, such as plaids. Demands, variable costs for each fabric, and production rates on the looms are given in the table below. The mill has 10 Northrop looms and 2 Jaquard looms. Any fabrics that cannot be woven in the mill because of limited capacity will be purchased from an external supplier, finished at the mill, and sold at the selling price. In addition to determining which looms to use to process the fabrics, the manager also needs to determine which fabrics to buy externally. Let Ji represent the number of yards of fabric i to be produced on Jaquard looms, and Ni be the number of yards of fabric i to be produced on Northrop looms.

Remington Textiles

Data

Fabric

Demand (yards)

Jaquard Capacity (hours/yard)

Northrop Capacity (hours/yard)

Mill Cost ($/yard)

Outsourcing Cost ($/hour)

1

50,000

0.2

NA

0.53

0.81

2

62,000

0.2

0.2

0.6

0.85

3

35,000

025

0.25

0.71

0.84

What is the correct constraint for expressing the capacity of Northrop looms?

Group of answer choices

0.2N2 + 0.25N3 ≤ 4032

0.2N2 + 0.25N3 ≤ 20160

5N1 + 5N2 + 5N3 ≤ 4032

5N1 + 5N2 + 4N3 ≤ 20160

Homework Answers

Answer #1

Ni is the number of yards of fabric i to be produced on Northrop looms.

For 12 weeks, number of hours, a Northrop loom will be running = 12 * 7 * 24 = 2016

Total capacity of 10 Northrop looms = 10 * 2016 = 20160

Total capacity to meet the demand of each fabric = 0.2N2 + 0.25N3

The constraint for expressing the capacity of Northrop looms is that the total capacity to meet the demand of each fabric should be at most 20160 hours which is,

0.2N2 + 0.25N3 ≤ 20160

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Remington Textiles has a mill that produces three types of fabrics on a make-to-order basis. The...
Remington Textiles has a mill that produces three types of fabrics on a make-to-order basis. The mill operates on a 24/7 basis. The key decision facing the plant manager is about the type of loom needed to process each fabric during the coming 12 weeks to meet demands for the three fabrics and not exceed the capacity of the looms in the mill. Two types of looms are used: Jaquard and Northrop. Jaquard looms can be used to make all...
Use the table below to answer the following question(s). Remington Textiles has a mill that produces...
Use the table below to answer the following question(s). Remington Textiles has a mill that produces three types of fabrics on a make-to-order basis. The mill operates on a 24/7 basis. The key decision facing the plant manager is about the type of loom needed to process each fabric during the coming 12 weeks to meet demands for the three fabrics and not exceed the capacity of the looms in the mill. Two types of looms are used: Jaquard and...
Use the table below to answer the following question(s). Remington Textiles has a mill that produces...
Use the table below to answer the following question(s). Remington Textiles has a mill that produces three types of fabrics on a make-to-order basis. The mill operates on a 24/7 basis. The key decision facing the plant manager is about the type of loom needed to process each fabric during the coming 12 weeks to meet demands for the three fabrics and not exceed the capacity of the looms in the mill. Two types of looms are used: Jaquard and...
The textile mill model - Produces 3 types of fabric (F1, F2, F3) on 2 types...
The textile mill model - Produces 3 types of fabric (F1, F2, F3) on 2 types of machines (Regular, Special). Or Buy. Time to delivery is 13 weeks. 15 regular machines (F2, F3) + 3 special machines (F1, F2, F3) + Buy (F1, F2, F3) Demand for F1, F2, F3 is 45000, 76500, 10000 yards. Special loom capacity in yards/hour – 4.7, 5.2, 4.4 Regular loom capacity in yards/hour – 0, 5.2, 4.4 Manufacture cost in $/yard – 0.65, 0.61,...