Question

Compute the reliability of a system with 4 components in standby parallel configuration, with failure rate...

Compute the reliability of a system with 4 components in standby parallel configuration, with failure rate of 0.000346 after 7600 hours of operation.

Correct Answer: 0.729547242

Please solve without using excel.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the reliability of a system with 4 components in standby parallel configuration, with failure rate...
Compute the reliability of a system with 4 components in standby parallel configuration, with failure rate of 0.000346 after 7600 hours of operation ANSWER: 0.729547242 PLEASE SHOW ALL WORK
Compute the reliability of a system with 4 components in series configuration, with failure rate of...
Compute the reliability of a system with 4 components in series configuration, with failure rate of 0.000471 after 860 hours of operation I need correct answer please!
Compute the reliability of a system with 7 components, neading with at least 2 in full...
Compute the reliability of a system with 7 components, neading with at least 2 in full operation with the MTTF of each component being 2100 hours, after 2510 hours of operation Correct Answer: 0.676128323 Please solve without using excel. Please show all work.
A system consists of n identical components in parallel with each component having a reliability of...
A system consists of n identical components in parallel with each component having a reliability of p. The failure events of the components can be assumed to be independent. Compute the reliability of the system as functions of p and n. Plot system reliability as functions of p and n for the ranges of p = [0.9, 0.99, 0.999] and n = [3, 5, 10, 100, 1000].
The electrical system for an assembly line has four components arranged in two parallel subsystems as...
The electrical system for an assembly line has four components arranged in two parallel subsystems as shown in the diagram below. Each of the four components (labeled 1, 2, 3, 4) are independent and each has a 10% chance of failure. Because the components are independent, the two subsystems (labeled A and B) are also independent. If one component in a subsystem fails, then the whole subsystem fails because the power cannot get through. However, because there are two subsystems,...
The principle of redundancy is used when system reliability is improved through redundant or backup components....
The principle of redundancy is used when system reliability is improved through redundant or backup components. Assume that a​ student's alarm clock has a 18.7 ​% daily failure rate. Complete parts​ (a) through​ (d) below. a. What is the probability that the​ student's alarm clock will not work on the morning of an important final​ exam? nothing ​(Round to three decimal places as​ needed.) b. If the student has two such alarm​ clocks, what is the probability that they both...
A manufacturing company is considering switching to an advanced robotics system that will reduce the labor...
A manufacturing company is considering switching to an advanced robotics system that will reduce the labor cost in a given factory. The initial cost is $175,000 with annual costs of $45,000 and savings of $75,000 in the first year. Savings are projected to increase by $2500 annually after Year 1. The salvage value 10 years from now is projected to be $25,000. What rate of return will the factory make on this investment? Round your answer to the nearest tenth...
1. Suppose a drug is administered to a patient through an intravenous line at a rate...
1. Suppose a drug is administered to a patient through an intravenous line at a rate of r mg/hr. The rate at which the drug is metabolized causes the patient to eliminate 5% of the amount of the drug in their system per hour. Let y(t) represent the amount of the drug in the patients system t hours after it began to be administered.   a) write a first-order differential equation involving the function y that represents the situation along with...
1. Answer EITHER part (a) OR part (b). (a) A gas scrubber on an oilrig discharged...
1. Answer EITHER part (a) OR part (b). (a) A gas scrubber on an oilrig discharged gas periodically such that an accumulation of hydrocarbon gas nearby had occurred. A contractor welder was dispatched to a job immediately adjacent to the area and it being a shift change and personnel unavailable temporarily, the welder decided to commence welding. As a consequence, an incident occurred. Describe briefly: (i) what you imagine was the incident including any hazards existing prior to or during...
The Eagles Corporation uses a normal job-order costing system in its only production department. Overhead is...
The Eagles Corporation uses a normal job-order costing system in its only production department. Overhead is applied to jobs by a plant-wide overhead rate based on direct labor hours. The first year of operation began on December 1, 2016. During the month of December, Eagles Corporation purchased direct material with a total cost of $4,000. Of the $4,000, Eagles Corporation used $500 on Job 100. Job 100 was the only job worked during the month of December. Eagles Corporation also...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT