Question

When implementing a lean production system a stabilized schedule is achieved using which of the following?...

  1. When implementing a lean production system a stabilized schedule is achieved using which of the following?
    1. Level scheduling
    2. Demand pull
    3. Freeze window
    4. Reduced lot sizes
    5. Bottom-round management
  2. In implementing a lean production system you should work with suppliers to do which of the following?
    1. Open facilities near your factory
    2. Focus workstation capacities
    3. Backflush
    4. Provide quality at the source
    5. Reduce lead times
  3. In implementing a lean production system you should work with suppliers to do which of the following?
    1. Calculate lead times
    2. Quality circles
    3. Freeze window
    4. Make frequent deliveries
    5. Achieve bottom-round management
  4. In setting up a Kanban control system you need to determine the number of Kanban containers needed. If the expected demand during lead time is 25 per hour, the safety stock is 20% of the demand during lead time, the container size is 5, and the lead time to replenish an order is 5 hours, what is the number of Kanban containers needed?
    1. 5             
    2. 20           
    3. 27           
    4. 30           
    5. 34

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all...
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all correct answers. A. A Level Production Strategy minimizes the need for extra capacity and allows for smooth labor operations. B. The MPS is the tie between production and sales. C. A drawback about applying a Chase Demand Strategy is that it may lead to high levels of inventory when demand is low. D. The MPS allows sales to know the Availability to Promise (ATP)...
Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from...
Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from two different suppliers. The parts are needed throughout the entire 52-week year. Tegdiws are used at a relatively constant rate and are ordered whenever the remaining quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every five weeks. Data for both products are as follows:   ITEM TEGDIW WIDGET   Annual demand 13,000 6,000   Holding cost (% of item cost)...
QUESTION 1 Which of the following best exemplifies offshoring? A. A U.S. company employs foreign nationals...
QUESTION 1 Which of the following best exemplifies offshoring? A. A U.S. company employs foreign nationals at its U.S. based headquarters. B. A U.S. company translates novels originally written in foreign languages into English for distribution in the U.S. market. C. A U.S. company starts a chain of fusion restaurants to cater to the American public’s evolving palates. D. A U.S. company purchases footwear made in Europe to distribute to retailers in the United States. E. A U.S. company that...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of a specific product in the past three years. Quarter Year 1 2 3 4 2015 350 254 176 228 2016 367 258 169 236 2017 342 250 166 228 Predict demand in quarter 1 and quarter 2 of 2018, given that the demand forecast for the whole year is a total of 1,040 units. Question 6: DRP (8 p) A central DC supplies a...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer was Ford Motor Company. Como had a reputation for delivering a quality product. During the 1980s and the early 1990s, Como’s business grew because of its commitment to quality. Emphasis was on manufacturing operations, and few attempts were made to use project management. All work was controlled by line managers who, more often than not, were overburdened with work. The culture at Como underwent...
How can differential analysis be applied here to determine if it would be profitable to invest...
How can differential analysis be applied here to determine if it would be profitable to invest in new equipment to increase capacity for a constrained resource? KRAYDEN’S CYCLE COMPONENTS INTRODUCTION: COMPANY, PRODUCT, AND SUPPLY CHAIN Krayden’s Cycle Components (KCC) is a high-end specialty fabricator that manufactures one product with many variants. The basic product is known as a rolling chassis, a key component used in manufacturing motorcycles. While there are variations across the industry, a rolling chassis typically consists of...
QUESTION 1 (60) Read the case study below and answer the questions that follow. Transforming a...
QUESTION 1 (60) Read the case study below and answer the questions that follow. Transforming a pharmacy together: the Charlotte Maxeke Johannesburg Academic hospital. Before 2015, the patient experience at the Charlotte Maxeke Johannesburg Academic Hospital pharmacy went something like this: take the day off work to have your prescription filled; line up at dawn before the pharmacy opens in hopes of beating the rush; once inside, wait up to several hours for your prescription to be filled; or worse,...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft in the global market. The other major producer is European Airbus. Boeing produces three models in Everett, Washington: 747s, 767s, and 777s. The planes are all produced in the same building. At any one time, there may be as many as six planes in various stages of production. Obviously the building has to be fairly large to accommodate such a huge undertaking. In fact,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT