Question

Given this information: Expected demand during lead time = 285 units Standard deviation of lead time...

Given this information:
Expected demand during lead time = 285 units
Standard deviation of lead time demand = 16 units
Use Table.
Determine each of the following, assuming that lead time demand is distributed normally:

a. The ROP that will provide a risk of stockout of 1 percent during lead time. (Round your answer to the nearest whole number.)

ROP             units
  
b. The safety stock needed to attain a 1 percent risk of stockout during lead time. (Do not round intermediate calculations. Round your answer to the nearest whole number.)

Safety stock             units

c-1.
Would a stockout risk of 4 percent require more or less safety stock than a 1 percent risk?

  • More

  • Less



c-2.
Would the ROP be larger, smaller, or unaffected if the acceptable risk were 4 percent instead of 1 percent?
  

  • Unaffected

  • Larger

  • Smaller

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A product with an annual demand of 1100 units has Co = $24.5 and Ch =...
A product with an annual demand of 1100 units has Co = $24.5 and Ch = $7. The demand exhibits some variability such that the lead-time demand follows a normal probability distribution with µ = 30 and σ = 6. What is the recommended order quantity? If required, round your answer to two decimal places. Q* = What are the reorder point and safety stock if the firm desires at most a 3% probability of stock-out on any given order...
A product with an annual demand of 1000 units has Co = $25.5 and Ch =...
A product with an annual demand of 1000 units has Co = $25.5 and Ch = $8. The demand exhibits some variability such that the lead-time demand follows a normal probability distribution with µ = 25 and σ = 5. What is the recommended order quantity? If required, round your answer to two decimal places. Q* = __________ What are the reorder point and safety stock if the firm desires at most a 2% probability of stock-out on any given...
Daily demand for a product is 110 units, with a standard deviation of 20 units. The...
Daily demand for a product is 110 units, with a standard deviation of 20 units. The review period is 5 days and the lead time is 6 days. At the time of review there are 50 units in stock. If 90 percent service probability is desired, how many units should be ordered? (Use Excel's NORMSINV() function to find the correct critical value for the given ?-level. Do not round intermediate calculations. Round "z" value to 2 decimal places and final...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20...
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20 units and a standard deviation of 7. The supplier, Suits Galore, takes on average about 9 days to supply a MegaMart order. The standard deviation of lead time is 3 days. MegaMart is targeting a customer service level of 95 percent (z = 1.65) and monitors its inventory continuously. How much safety inventory of neckties should MegaMart carry? What should their reorder point (ROP)...
Use the information in the following table to answer the questions below: Demand 100 units per...
Use the information in the following table to answer the questions below: Demand 100 units per week Standard deviation of weekly demand 10 units Average lead time 10 days Standard deviation of the lead time 5 days Cycle service level 70 % Considering a continuous review system, Find the standard deviation of demand during the lead time. Find the safety stock. What is the reorder point?
Lead Time Demand for an item we keep in stock is 420 units, with a standard...
Lead Time Demand for an item we keep in stock is 420 units, with a standard deviation of 44 units. What service level is achieved with our current Reorder point of 442 units? What Reorder Point should be used in order to accomplish a service level of 97%?
Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a...
Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a normal distribution with a mean of 25 gallons per week and a standard deviation of 3.4 gallons per week. The new manager desires a service level of 90 percent. Lead time is two days, and the dairy is open seven days a week. (Hint: Work in terms of weeks.) Use Table B and Table B1. b-2. What is the probability of experiencing a stockout...
The reorder point r = dm is defined as the lead-time demand for an item. In...
The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with...
Ace Manufacturing produces commercial lawnmowers units in batches. the company estimates the demand for the year...
Ace Manufacturing produces commercial lawnmowers units in batches. the company estimates the demand for the year is 10,000 units. It costs about $80 to set up the manufacturing process, and the carrying cost is about 70 cents per unit per year. When the production process has been set up, 120 lawnmowers units can be made daily. The demand during the production period is approximately 60 units per day. The company operates its production area 167 days per year and includes...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT