Is it better to go to one fast server or several slower
servers?
Would you rather go to a server that can process customers at a
rate of 30 per hour or to a line feeding a five-server system that
can serve 6 customers per hour? Assume an arrival rate of 25
customers per hour. Which do you choose and why?
This is really two problems that we will compare: M/M/1 vs. M/M/S.
Start by writing down the information that you know, then plug in
that information into the appropriate formulas from the class
notes. For Wq and Ws, convert the results to minutes by multiplying
by 60 min/hr but only use the values in hours in the formulas. For
the M/M/s model, round / to one decimal place and obtain P0 and
Lq from the Infinite Source Table on pages 826-827 of the
text.
M/M/1
= _________ = _________
P0 =
Lq =
Ls =
Wq =
Ws =
M/M/s
= _________ / = _________ = _________ M = _________
P0 = __________
Lq = __________
Ls =
Wq =
Ws =
Which model is better, the M/M/1 or M/M/s?
Why?