Question

Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be...

Problem 12-09 (Algorithmic)

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:


Activity
Activity Time
(weeks)

Probability
A 7 0.30
8 0.31
9 0.23
10 0.16
B 5 0.16
7 0.57
9 0.27
C 8 0.11
10 0.20
12 0.35
14 0.22
16 0.12
D 12 0.60
14 0.40
  1. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
    Activity Base case Worst case Best case
    A weeks weeks weeks
    B weeks weeks weeks
    C weeks weeks weeks
    D weeks weeks weeks
    Total weeks weeks weeks
  2. Use the random numbers 0.1, 0.7455, 0.4873 and 0.2453 to simulate the completion time of the project in weeks.
    Activity Random Number Completion Time
    A 0.1 weeks
    B 0.7455 weeks
    C 0.4873 weeks
    D 0.2453 weeks
    Total weeks
  3. Discuss how simulation could be used to estimate the probability that the project can be completed in weeks or less.

    Simulation provides a distribution of project completion times. The   of times weeks and under can be used to estimate the probability that the project will be completed within weeks.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 7 0.30 8 0.31 9 0.23 10 0.16 B 5 0.16 7 0.57 9 0.27 C 8 0.11 10 0.20 12 0.35 14 0.22 16 0.12 D 12 0.60 14 0.40 Provide the base-case, worst-case, and best-case calculations for the...
A project has three activities A, B, and C that must be carried out sequentially. -----...
A project has three activities A, B, and C that must be carried out sequentially. ----- A -----> ----B----> ------C------> The probability distributions of the times required to complete each of the activities A, B, and C are uniformly distributed in intervals (1,5], (2,8] and (3,6] days respectively. The project completion time is the sum of times to finish all three activities. Run 1000 simulation trials in Excel to simulate the project. Which of the following Excel functions would generate...
(All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities...
(All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.25 6 0.35 7 0.25 8 0.15 B 3 0.20 5 0.55 7 0.25 C 10 0.10 12 0.25 14 0.40 16 0.20 18 0.05 D 8 0.60 10 0.40 (a)...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
HW8-Ch2-Executing Strategy: Project Management 1. A computer-system installation project consists of eight activities. The immediate predecessors...
HW8-Ch2-Executing Strategy: Project Management 1. A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are as follows: Activity Immediate Predecessors Activity Time A — 2 B — 7 C A 3 D A, C 6 E C 5 F D, E 2 G B, C 10 H G 4 What is the critical path? What is the project complete time? a. BCDEF; 22 weeks b. ACEF; 23 weeks c. BGH; 21 weeks 2....
Problem 14-1 (All answers were generated using 1,000 trials and native Excel functionality.) The management of...
Problem 14-1 (All answers were generated using 1,000 trials and native Excel functionality.) The management of Brinkley Corporation is interested in using simulation to estimate the profit per unit for a new product. The selling price for the product will be $55 per unit. Probability distributions for the purchase cost, the labor cost, and the transportation cost are estimated as follows: Procurement Cost ($) Probability Labor Cost ($) Probability Transportation Cost ($) Probability 11 0.25 22 0.15 4 0.65 12...
Problem #5 An IT project requires 6 activities. The table below displays the expected time and...
Problem #5 An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $2,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using LS times.
A project contains activities D and K. Activity D has 5 hours of slack, and activity...
A project contains activities D and K. Activity D has 5 hours of slack, and activity K has 7 hours of slack. If activity D is delayed 4 hours, activity K is delayed 6 hours, and these are the only delays, then the overall effect of these delays is to delay the minimum project completion time by: Select one: a. 2 hours b. 0 hours c. The overall delay cannot be determined with only this information d. 11 hours