Problem 12-09 (Algorithmic)
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
Activity |
Activity Time (weeks) |
Probability |
||
A | 7 | 0.30 | ||
8 | 0.31 | |||
9 | 0.23 | |||
10 | 0.16 | |||
B | 5 | 0.16 | ||
7 | 0.57 | |||
9 | 0.27 | |||
C | 8 | 0.11 | ||
10 | 0.20 | |||
12 | 0.35 | |||
14 | 0.22 | |||
16 | 0.12 | |||
D | 12 | 0.60 | ||
14 | 0.40 | |||
Activity | Base case | Worst case | Best case |
---|---|---|---|
A | weeks | weeks | weeks |
B | weeks | weeks | weeks |
C | weeks | weeks | weeks |
D | weeks | weeks | weeks |
Total | weeks | weeks | weeks |
Activity | Random Number | Completion Time |
---|---|---|
A | 0.1 | weeks |
B | 0.7455 | weeks |
C | 0.4873 | weeks |
D | 0.2453 | weeks |
Total | weeks |