Question

Which of the following are activities and which are work packages? Project Plan Prepare the purchase...

  1. Which of the following are activities and which are work packages?
    1. Project Plan
    2. Prepare the purchase order for a router
    3. System Design Package
    4. Install the foundation

Homework Answers

Answer #1

An activity is smallest unit that can be achieved without further breaking it down into sub-activities. A work package is a composition or combination of activities in a sequence. So Work package will be at a higher level in Work Breakdown Structure(WBS)

a) Project Plan : It is a work package since the project plan has several components like scope, objectives etc.

b) Prepare the purchase order for a router : it is an activity since it doesn't involve any sub-activities

c) System Design Package : It is a work package since it a collection of classes, relationships, use-cases etc

d) Install the foundation : It is an activity, since we just install the foundation and it doesn't have any sub activities

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Horizons, Inc. sells mobile phones, wireless plans, and service plan packages. Horizons packages the following items...
Horizons, Inc. sells mobile phones, wireless plans, and service plan packages. Horizons packages the following items for sale. Package                    Amount       Description Phone                         $199.00       Paid when customer purchases the phone. Wireless Plan per month 40.00       Unlimited calling. Minimum coverage of 12-months. Paid monthly. Service Plan per month   24.00       12-month coverage. Paid when customer purchases the phone. Total When Purchased$263.00 Horizons has determined that each item is a separate performance obligation. A customer purchases a new phone package on September...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Insert the correct predecessor function using Microsoft Project for the following question: "Work may not start...
Insert the correct predecessor function using Microsoft Project for the following question: "Work may not start on basement until work on foundation is 50% complete. Work on basement may not proceed past 70% until work on foundation is 100% complete."
You plan to purchase a property which has an expected NOI of $200,000. You plan to...
You plan to purchase a property which has an expected NOI of $200,000. You plan to borrow $1,500,000 at a 5% annual rate for 30 years. What is the DCR for this investment? If the property in #9 is being purchased at an 8% cap rate, assuming the same loan information what is the LTV for this purchase? show work
(Project Management) Q1) Create WBS (Work-breakdown structure) for Mobile Application Development Project. Application should be able...
(Project Management) Q1) Create WBS (Work-breakdown structure) for Mobile Application Development Project. Application should be able to allow passengers to have self-check-in at airports. Q2) Create Design Structure Matrix (DSM) using listed tasks created in Q1. Find the activities which are dependent upon each other.
which of the following is not a result of assigning service activities to a work center...
which of the following is not a result of assigning service activities to a work center rather than a centralized service department? A)workers better understand the production process and their machinery B)service machinery is eliminated C) product quaility improves D) repairs and maintenance costs are decreased E) workers tend to take better care of their machinery
develop a 2 year schedules/plan which identifies at least 6 initiatives and activities that you would...
develop a 2 year schedules/plan which identifies at least 6 initiatives and activities that you would undertake that will assist you to develop and maintaining your skills to ensure effective internal and external work place relationships . 1. identify at least 3 initiatives for internal and external work place relationships
Which of the following plan combinations will allow you to make $19,500 deferrals into each plan?...
Which of the following plan combinations will allow you to make $19,500 deferrals into each plan? 403(b) and 401(k) SIMPLE and SEP Pension Plan and Money Purchase Plan 401(k) and 457
You work for Microsoft in their global smart phone group. You have been made project manager...
You work for Microsoft in their global smart phone group. You have been made project manager for the design of a new smart phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!      You have been given the information in Exhibit 5.13. It includes all the...
Which of the following laid the foundation for the self managed work teams of today A)...
Which of the following laid the foundation for the self managed work teams of today A) special purpose teams B) command teams C) production teams D) informal groups E) friendship groups
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT