Statewide Auto Parts uses a four-week periodic review system to reorder parts for its inventory stock....

Statewide Auto Parts uses a four-week periodic review system to reorder parts for its inventory stock. A one-week lead time is required to fill the order. Demand for one particular part during the five-week replenishment period is normally distributed with a mean of 20 units and a standard deviation of 8 units. Do not round intermediate calculations.

  1. At a particular periodic review, 7 units are in inventory. The parts manager places an order for 20 units. What is the probability that this part will have a stock-out before an order that is placed at the next four-week review period arrives? If required, round your answer to four decimal places.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider a periodic review inventory system with a lead time of two weeks and a review...
Consider a periodic review inventory system with a lead time of two weeks and a review period of seven weeks. The standard deviation of weekly demand is 20 and the desired service level is 86%. Annual demand is 36,000 units and there are 50 weeks in the year. Currently, on hand inventory is 630 units. What should be the order quantity?
The local Giant store uses a periodic review model to stock their paper towels. After collecting...
The local Giant store uses a periodic review model to stock their paper towels. After collecting some data, the firm was able to establish that the daily demand for paper towels is 9 packs. The store reviews its inventory once a week and places an order on Sunday. The inventory for this week at the time of order placement is 4. The lead time to get the product from the local distribution center is 1 days. What should be the...
A manufacturing company keeps stock of replacement parts for its critical equipment. The lead time for...
A manufacturing company keeps stock of replacement parts for its critical equipment. The lead time for a rare $500 part is 2 months. The maintenance manager keeps close track of the inventory of these parts and places a new order whenever the stock reaches a certain threshold or reorder point. When they order, they place orders of 20 units at a time because the supplier has to make a special production run for it. From past history they estimate that...
Jake, Inc. begins a review of ordering policies for its continuous review system by checking the...
Jake, Inc. begins a review of ordering policies for its continuous review system by checking the current policies for a sample of its A items. Following are the characteristics of one item: Demand (D) = 94 units/week (assume 52 weeks per year) Ordering and setup cost (S) = $720/order Holding cost (H) = $23/unit/year Lead time (L) = 3 weeks Standard deviation of weekly demand = 30 units Cycle-service level = 82 percent Develop the best policies for a periodic-review...
You manage inventory for your company and use a continuous review inventory system to control reordering...
You manage inventory for your company and use a continuous review inventory system to control reordering items for stock. Your company is open for business 300 days per year. One of your most important items experiences demand of 20 units per day, normally distributed with a standard deviation of 3 units per day. You experience a lead time on orders from your supplier of six days with a standard deviation of two days. The unit price, regardless of order size,...
Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from...
Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from two different suppliers. The parts are needed throughout the entire 52-week year. Tegdiws are used at a relatively constant rate and are ordered whenever the remaining quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every five weeks. Data for both products are as follows:   ITEM TEGDIW WIDGET   Annual demand 13,000 6,000   Holding cost (% of item cost)...
Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in...
Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in its manufacturing operation from a variety of different suppliers. One particular supplier provides a part where the assumptions of the EOQ model are realistic. The annual demand is 2,500 units, the ordering cost is $40 per order, and the annual holding cost rate is 25%. (a) If the cost of the part is $20 per unit, what is the economic order quantity? (b) Assume...
The Churchill Corporation uses a periodic inventory system and the LIFO inventory cost method for its...
The Churchill Corporation uses a periodic inventory system and the LIFO inventory cost method for its one product. Beginning inventory of 23,200 units consisted of the following, listed in chronological order of acquisition: 13,600 units at a cost of $9.00 per unit = $122,400 9,600 units at a cost of $10.00 per unit = 96,000 During 2021, inventory quantity declined by 13,200 units. All units purchased during 2021 cost $13.00 per unit. Required: Calculate the before-tax LIFO liquidation profit or...
Mist, Inc. uses a PERIODIC inventory system and has the following transactions for one of its...
Mist, Inc. uses a PERIODIC inventory system and has the following transactions for one of its inventory items during 2020: Beginning Inventory 108 units @ $51 per unit Purchases Purchase 1 on 3/11/20 60 units @ $53 per unit Purchase 2 on 10/18/20 109 units @ $55 per unit Sales Sale 1 on 3/15/20 100 units @ $78 per unit Sale 2 on 10/22/20 135 units @ $78 per unit All units sold on 3/15/20 were from beginning inventory. The...
A company begins a review of ordering policies for a sample of items. The company operates...
A company begins a review of ordering policies for a sample of items. The company operates 52 weeks a year. The following are the characteristics of one item: Demand = 3,380 units/year Ordering cost = $50/order Holding cost = $13/unit/year Lead time = 3 weeks Standard deviation of weekly demand = 16 units Desired cycle service level = 98% a) Calculate EOQ and use it to find the order interval (OI). Round the number to the nearest integer week. Hint:...