The project of an interior design upgrade at one of the Citibank branches consists of six activities. The tasks, durations (in days), and predecessor relationships are as follow:
Activity | Immediate Predecessors | Activity Time |
A | - | 3 |
B | A | 4 |
C | A | 5 |
D | B, C | 4 |
E | C | 3 |
F | D, E | 3 |
Calculate the slack times and identify the critical path(s).