Question

ProCycle & Co. uses X bar and R-charts to track the thickness of bicycle brake pads...

ProCycle & Co. uses X bar and R-charts to track the thickness of bicycle brake pads in millimeters. Below are the observations for 5 samples. What are the UCLR , LCLR (for range) and X bar (double bar)?

Sample Observation 1 Observation 2 Observation 3
1 22 14 12
2 24 17 18
3 19 20 21
4 16 13 15
5 10 10 13

Group of answer choices

7.722: 0: 81.34

9.575: 0: 81.34

7.222: 0: 81.34

12.87; 0: 16.266

10.666: 0: 16.266

Homework Answers

Answer #1
Sample Observation 1 Observation 2 Observation 3 average range
1 22 14 12 16.00 10.00
2 24 17 18 19.67 7.00
3 19 20 21 20.00 2.00
4 16 13 15 14.67 3.00
5 10 10 13 11.00 3.00
average 16.27 5.00
Range chart
average range R̅ = 5
sample size n   = 3
for sample size n=3, criitcal value of constant D3= 0
for sample size n=3, criitcal value of constant D4= 2.575
control line (CL) = R̅= 5
upper control limit (UCL)=D4R̅ = 12.8750
lower control limit(LCL) =D3R̅ = 0.00000

from above UCLR =12.875

LCLR =0

and Xbar =16.266

therefore corerct option is: 12.87; 0: 16.266

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following data is X-Bar and R values for 12 samples of size n = 5....
The following data is X-Bar and R values for 12 samples of size n = 5. They were taken from a process measuring various inductance values for a new production line of high fidelity speakers. Subgroup No., (X-Bar), ((Range)) 1 (345) ((13)), 2 (347) ((14)), 3 (350) ((12)), 4 (346) ((11)), 5 (350) ((15)), 6 (345) ((16)), 7 (349)((14)), 8 (348) ((13)), 9 (348)((12)), 10 (354) ((15)), 11 (352) ((13)), 12 (355) ((16)) Create X-Bar and R control charts from...
A hospital is using X bar and R charts to record the time it takes to...
A hospital is using X bar and R charts to record the time it takes to process account information. A sample of five applications is taken each day. The first four weeks’ (20 days’) data give the following values: X-double bar= 17 min, R bar = 7 min. If the upper and lower specification limits are 21 minutes and 13 minutes respectively, calculate Cp and Cpk. Interpret the indices
Below are X-bar and R values for 12 samples of size = 5. They are taken...
Below are X-bar and R values for 12 samples of size = 5. They are taken from a process producing bearings. The measurements are made on the inside diameter of the bearing. The data have been coded from 0.50; in other words, a measurement of 0.50345 has been recorded as 345. Range values are coded from 0.000; that is, 0.00013 is recorded as 13. Subgroup Number X-bar Range 1 145 13 2 147 14 3 150 12 4 146 11...
Please compute the value, upper control limit, and lower control limit for the x-bar chart, r-bar...
Please compute the value, upper control limit, and lower control limit for the x-bar chart, r-bar chart, p chart, and np chart. Sample # Observations Defects 1 44 49 44 44 40 0 2 42 46 51 51 42 2 3 45 45 49 49 46 2 4 40 39 42 42 47 7 5 44 51 53 53 44 2 6 41 44 43 43 46 8 7 40 44 46 46 48 3 8 54 49 48 48...
Consider the observations jointly taken on the binary random variables X and Y given in the...
Consider the observations jointly taken on the binary random variables X and Y given in the “Problem 1” worksheet in the Excel spreadsheet titled “Sheet 1”. 1. Organize the data in a two-way table by counting the number of observations that fall within each of the following cells: {X = 0, Y = 0}, {X = 0, Y = 1}, {X = 1, Y = 0}, and {X = 1, Y = 1}. 2. Use observed cell counts found in...
Based on your recommendations, Mr. Miller improved shop operations and successfully reduced the number of customer...
Based on your recommendations, Mr. Miller improved shop operations and successfully reduced the number of customer complaints. To maintain good service, Mr. Miller asked you to keep monitoring the wait times of oil change customers at the shop. First, you decide to create an x-bar chart to monitor the central tendency (i.e., mean). But you know that we sometimes overlook a problem if we use only an x-bar chart. Therefore, you decide to create an R-chart to monitor the process...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how the firms resources incompetencies support the given pressures regarding costs and local responsiveness. Describe entry modes have they usually used, and whether they are appropriate for the given strategy. Any key issues in their global strategy? casestudy: Atlanta, June 17, 2014. Sea of Delta employees and their families swarmed between food trucks, amusement park booths, and entertainment venues that were scattered throughout what would...