If a process operates at 1.80 σ-quality performance level, what is the percentage of the specification...

If a process operates at 1.80 σ-quality performance level, what is the percentage of the specification band that the process uses up?

Homework Answers

Answer #1

Answer:

The percentage of the specification band that the process uses up = 92.81%

Explanation:

The sigma value for the specification limit = 1.8 which means the mean value can be differed by 1.8 standard deviations on either side.

The percentage of the specification band that the process uses up is within the 1.8 standard deviations from the mean is obtained by from the z distribution table,

.

The values are obtained in excel. The screenshot is shown below,

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Suppose that the specification limits for a production process are LSL = 0.02 and USL =...
Suppose that the specification limits for a production process are LSL = 0.02 and USL = 0.10, with the nominal specification being 0.06. a)_____________ What is the sigma level if the process standard deviation is 0.01. b)_____________ If the process is centered, what is the DPMO? can you show me how to do it in excel? what variables do I use? thank you
need answer to these true-false questions. 1-) When the sample size n is moderately large, say...
need answer to these true-false questions. 1-) When the sample size n is moderately large, say n > 10 or 12, x̅ and R charts are preferable to X̅ and s charts. 2-) If Cp >1, the process uses up more than 100% of the specification band 3-) An assumption in the performance properties of x̅ and R control charts is that the underlying distribution of the quality characteristic is normal. 4-) Average time to signal is the expected number...
Examine the following data and determine if the process is capable using a specification of 2.100...
Examine the following data and determine if the process is capable using a specification of 2.100 +/-0.017. Assume sst = 0.0044. 2.095            2.090            2.119 2.096            2.092            2.110 2.090            2.102            2.113 2.095            2.098            2.100 2.089            2.095            2.099 2.081            2.102            2.104 2.080            2.101            2.102 2.092            2.099            2.106 2.094            2.102            2.119 2.093            2.118            2.118 What is the long term standard deviation? What is the capability index and ratio? What is the process performance index and ratio? Is the process capable? Why?
1. A quality engineer needs to estimate the percentage of bolts manufactured on a certain day...
1. A quality engineer needs to estimate the percentage of bolts manufactured on a certain day that meet a strength specification. At 3:00 p.m. he samples the last 100 bolts to be manufactured. (12 points) a. What is the population? b. What is the sample? c. Is the sample likely to be representative? Explain your answer, and if you determine it is not, describe a method that would be more representative.
True/False: For statements 1 through 6, state true or false From a quality perspective, a process...
True/False: For statements 1 through 6, state true or false From a quality perspective, a process is said to be a “capable” process if capacity (supply) exceeds customer demand.                           [ Select ]                       ["True", "Flase"]       If a process is not a capable process, then it is better to achieve a good Cpk for this process, before achieving a good Cp.              ...
In a normal distribution, μ = 1400 and σ = 90. Approximately, what percentage of scores...
In a normal distribution, μ = 1400 and σ = 90. Approximately, what percentage of scores lie between 1310 and 1445? In a population of normally distributed scores, μ = 70 and σ = 24. Approximately what percentage of random samples of 36 scores would have means with a value in the range 64 to 76?
As part of the process for improving the quality of their cars, Toyota engineers have identified...
As part of the process for improving the quality of their cars, Toyota engineers have identified a potential improvement to the process that makes a washer that is used in the accelerator assembly. The tolerances on the thickness of the washer are fairly large since the fit can be loose, but if it does happen to get too large, it can cause the accelerator to bind and create a potential problem for the driver. (Note: This part of the case...
A production process operates with 1% nonconforming output. Every hour a sample of 30 units of...
A production process operates with 1% nonconforming output. Every hour a sample of 30 units of product is taken, and the number of nonconforming units counted. If one or more nonconforming units are found, the process is stopped and the quality control technician must search for the cause of nonconforming production. What is the probability that one or more nonconforming units are found? (hint: binomial distribution)
Given the data below, a lower specification of 52.8, and an upper specification of 72.2, what...
Given the data below, a lower specification of 52.8, and an upper specification of 72.2, what is the long term process performance (Ppk)? Please provide answer to at least 3 significant digits. Data 50.65897 56.33776 55.34139 67.1965 64.90829 49.54292 50.85892 53.96954 57.93657 52.40427 56.36876 52.91792 63.24705 55.3842 58.26031 59.06518 64.87003 43.09846 52.72188 49.80689 42.68165 53.95463 59.33698 64.51836 61.96437 59.39377 49.07404 57.32518 59.24585 56.47081 49.56036 57.80438 65.01286 53.66745 64.72979 54.76287 58.44208 53.61521 55.92805 67.20384 63.03314 53.92972 48.73767 62.77028 52.02327 64.74119 57.90265...
Medication Error What do you think the hypothetical effect of the quality or performance initiative will...
Medication Error What do you think the hypothetical effect of the quality or performance initiative will be on the culture of safety within the organization?