Question

A project with nine activities includes only four paths that are shown below along with their...

A project with nine activities includes only four paths that are shown below along with their lengths. The following table provides the opportunities for crashing activities.

Activity

Maximum Reduction

Crash Cost/Day

A

2

$900

B

-

-

C

-

-

D

2

$200

E

2

$400

F

2

$700

G

1

$500

H

-

-

I

2

$800

Suppose each day of shortening (crashing) the project saves $1200. Determine how many days should the project be crashed, and report the total cost for this crashing and how long the project will take to complete after the crashing.

Show all your work.

Cost for crashing = ____________

How long is the project after crashing?   ____________

Paths   

Length in days

continue......

A E I

26

A E G

25

B C F

22

B D F   I

27

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
Consider the table below, which includes time and activity data for a Small IT Project. All...
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project. Activity Duration (Days) Predecessor A 8 - B 10 A C 18 A D 4 A E 28 B, D F 2 C, E G 32 E H 18 B I 12 F J 2 H, G, I Draw a network diagram representing the project. MS PowerPoint or...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days? b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days? c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days? d) What is the...
Given the data table below develop the precedence network and perform the CPM calculations. Then, using...
Given the data table below develop the precedence network and perform the CPM calculations. Then, using the proposed crashing strategy calculate the normal, least-cost, and crash duration for the project below. Calculate the cost associated with each duration. Indirect cost (overhead) is $120 per day. Activity IPA Duration Cost $ Normal Crash Normal Crash A - 5 4 $770 $900 B - 3 2 $660 $700 C A 7 4 $800 $1,070 D A,B 4 3 $1,000 $1,110 E B...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D J 3 F K 8 E,H L 4 C,J (a) How long the project will take? (b) State the critical activities. (c)...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time columns in the table. Units: Time is in days, cost is in $. Activity Immediate predecessor(s) Time Cost Crash Time Crash Cost Time Reduction Cost to Crash A -- 10 5000 10 5000 B A 12 1200 11 1300 C A 11 3600 9 4800 D B 5 300 4 600 E C 8 1000 6 2000 F E 9 2400 7 5400 G...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...