Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:
Immediate | ||
Activity | Predecessor | Time |
A | — | 3 |
B | — | 4 |
C | — | 2 |
D | A, B, C | 2 |
E | A, D | 8 |
F | C, D | 7 |
G | D, E | 5 |
H | F | 7 |
a. draw the project network
b. what are the critical activities?
c. what activity has the most slack time?
d. will the project be completed by September 1? Project completion time?
Earliest | Latest | Earliest | Latest | Critical | ||||||||
Activity | Start | Start | Finish | Finish | Slack | Activity | ||||||
A | ||||||||||||
B | ||||||||||||
C | ||||||||||||
D | ||||||||||||
E | ||||||||||||
F | ||||||||||||
G | ||||||||||||
H |
Activity | ES | LS | EF | LF | slack | CRITICAL ACTIVITY |
A | 0 | 1 | 3 | 4 | 1 | |
B | 0 | 0 | 4 | 4 | 0 | YES |
C | 0 | 2 | 2 | 4 | 2 | |
D | 4 | 4 | 6 | 6 | 0 | YES |
E | 3 | 7 | 11 | 15 | 4 | |
F | 6 | 6 | 13 | 13 | 0 | YES |
G | 11 | 15 | 16 | 20 | 4 | |
H | 13 | 13 | 20 | 20 | 0 | YES |
Get Answers For Free
Most questions answered within 1 hours.