Question

Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...

Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:

Immediate
Activity Predecessor Time
A 3
B 4
C 2
D A, B, C 2
E A, D 8
F C, D 7
G D, E 5
H F 7

a. draw the project network

b. what are the critical activities?

c. what activity has the most slack time?

d. will the project be completed by September 1? Project completion time?

  1. Earliest Latest Earliest Latest Critical
    Activity Start Start Finish Finish Slack Activity
    A
    B
    C
    D
    E
    F
    G
    H

Homework Answers

Answer #1
Activity ES LS EF LF slack CRITICAL ACTIVITY
A 0 1 3 4 1
B 0 0 4 4 0 YES
C 0 2 2 4 2
D 4 4 6 6 0 YES
E 3 7 11 15 4
F 6 6 13 13 0 YES
G 11 15 16 20 4
H 13 13 20 20 0 YES

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs — 13 8 30 130 B Order equipment A 9 6 120...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Sch.W Foundry, a metalwork plant in Quebec, has just decided to make a major investment in...
Sch.W Foundry, a metalwork plant in Quebec, has just decided to make a major investment in new air pollution control equipment. The plant, however, must be shut during this installation process. Sch.W’s board of directors estimates that the company can survive no more than 16 weeks without production in full swing. The managing partner wants to make sure the installation of the filtering system progresses smoothly and on time. The activities involved in the foundry project are presented in the...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less. TIME ESTIMATES (DAYS) ACTIVITY ACTIVITY PREDECESSOR a m b A - 5  8 17 B - 7 10 13 C A 3  5  7 D A 1  3  5 E B, C 4  6  8 F B, C 3  3  3 G D,E 3  ...