The data in below table lists country code and the order to remittance (OTR) time for hardware / software installations for the last 76 installations (from first to last). OTR is the time it takes from an order being placed until the system is installed and we receive payment (remittance). Because this company does business internationally, it also notes the country of installation using a country code. This code is listed in the first column.
Table: Country Code and OTR Cycle Time for Software Systems Installation
Country Code |
Cycle Time |
Country Code |
Cycle Time |
1 |
20 |
5 |
29 |
1 |
24 |
6 |
40 |
1 |
46 |
7 |
157 |
1 |
26 |
8 |
19 |
14 |
38 |
5 |
24 |
1 |
15 |
1 |
81 |
1 |
15 |
7 |
53 |
17 |
23 |
7 |
26 |
1 |
31 |
1 |
28 |
1 |
31 |
1 |
34 |
6 |
64 |
1 |
34 |
5 |
29 |
7 |
50 |
5 |
44 |
1 |
52 |
1 |
32 |
1 |
19 |
1 |
15 |
1 |
44 |
7 |
11 |
14 |
150 |
7 |
14 |
7 |
29 |
1 |
89 |
17 |
23 |
17 |
41 |
6 |
79 |
7 |
41 |
17 |
13 |
1 |
36 |
6 |
32 |
8 |
43 |
7 |
61 |
17 |
21 |
8 |
42 |
8 |
28 |
8 |
46 |
7 |
18 |
7 |
88 |
8 |
47 |
14 |
24 |
6 |
26 |
7 |
7 |
6 |
47 |
1 |
33 |
5 |
9 |
5 |
129 |
7 |
42 |
17 |
41 |
5 |
5 |
17 |
43 |
6 |
27 |
14 |
42 |
6 |
27 |
14 |
42 |
1 |
33 |
7 |
53 |
7 |
44 |
7 |
53 |
1 |
21 |
7 |
48 |
1 |
22 |
5 |
21 |
1 |
50 |
1 |
19 |
Use the date in table above and answer the following questions in the space provided below:
Number of samples | 76 |
Defects per sample | |
Upper Control Limit, UCL | 58.371 |
Center | 39.513 |
Lower Control Limit, LCL | 20.655 |
The c-chart is used.
The control chart is:
The process is out of control.
No, the country has no impact on installation time.