The data in the Excel sheet labeled 'Concrete' represent the compressive strength, in thousands of pounds per square inch (psi), of 20 samples of concrete taken two and seven days after pouring.
At the 0.01 level of significance, is there evidence that the mean strength is lower at two days than at seven days?
What test will you use?
What is the p-value?
Reject Ho?
Is there evidence of a lower strength?
Two days | Seven days | |
Sample | ||
1 | 3.8 | 4.07 |
2 | 3.135 | 3.605 |
3 | 3.205 | 3.59 |
4 | 2.985 | 3.475 |
5 | 2.71 | 3.67 |
6 | 3.425 | 4.03 |
7 | 2.895 | 3.25 |
8 | 2.855 | 3.355 |
9 | 3.295 | 3.43 |
10 | 2.935 | 3.63 |
11 | 3.035 | 3.595 |
12 | 3.115 | 3.675 |
13 | 2.68 | 3.805 |
14 | 2.845 | 4.53 |
15 | 2.75 | 3.25 |
16 | 2.205 | 2.28 |
17 | 3.065 | 3.63 |
18 | 2.895 | 2.915 |
19 | 2.06 | 2.945 |
20 | 2.63 | 2.85 |
please like if it helps me