Question

A project has the following tasks and duration estimates given. These three tasks are done in...

  1. A project has the following tasks and duration estimates given. These three tasks are done in succession on a project.

Task

Optimistic Estimate

Most Likely Estimate

Pessimistic Estimate

Alpha

30 days

40 days

50 days

Beta

20 days

25 days

28 days

Charlie

4 days

10 days

12 days

Delta

25 days

30 days

50 days

  1. What is the expected duration for the project? (3 points)

  1. What is the variance for the project? (3 points)

  1. What is the standard deviation of the project? (3 points)

  1. What is the range of the duration of the project given 3 sigma? (3 points)

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the following activities and their three duration estimates (in days) to do the following Determine...
Use the following activities and their three duration estimates (in days) to do the following Determine the expected duration of the project – use 2 decimals when determining the duratio Path Activity Optimistic Most Likely Pessimistic a-b-c A 4 5 6 B 7 8 10 C 3 5 9 d-e-f D 7 8 11 E 2 3 4 f 1 4 6
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
Consider the table below, which includes time and activity data for a Small IT Project. All...
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project. Activity Duration (Days) Predecessor A 8 - B 10 A C 18 A D 4 A E 28 B, D F 2 C, E G 32 E H 18 B I 12 F J 2 H, G, I Draw a network diagram representing the project. MS PowerPoint or...
Question 26 Given the data below, compute the standard deviation for stock B. Enter your answer...
Question 26 Given the data below, compute the standard deviation for stock B. Enter your answer in percentages rounded off to two decimal points.Do not enter % in the answer box. Event           Probability          Returns Pessimistic 25% 7% Most Likely 50% 15% Optimistic 25% 23% Flag this Question Question 27 Calculate the expected returns of your portfolio Stock Invest Exp Ret A $301 2.6% B $649 19.9% C $497 28% Note: Enter your answer in percentages rounded off to...
The project is estimated to be of 10 years duration. It involves setting up new machinery...
The project is estimated to be of 10 years duration. It involves setting up new machinery with an estimated cost of as much as Thai baht (THB) 375 million, including installation. This amount could be depreciated using the straight-line method (SLM) over a period of 10 years with a resale value of THB13.5 million. The project would require an initial working capital of THB 15.5 million. With the planned new capacity, the company would be able to produce 60,000 pieces...
The Women’s Health Nurse Practitioner evaluated Sara, a 17-year old female. Sara has not had a...
The Women’s Health Nurse Practitioner evaluated Sara, a 17-year old female. Sara has not had a menstrual period for 6 months. Her history reveals that menarche occurred at the age of 12 years, and her menses were regular at 28-day intervals until they became irregular 1 year ago. Sara is a member of her high school gymnastics team. She has been spending long hours training with the team, as she hopes to get a gymnastic scholarship at her “dream” university...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Julie Gates, a recent Finance graduate, has been hired as a financial analyst in Macroworld’s corporate...
Julie Gates, a recent Finance graduate, has been hired as a financial analyst in Macroworld’s corporate finance department. Macroworld is a large computer software and sometimes hardware & electronic gadget company. Julie’s first major assignment has her involved with the analysis of three different capital budgeting projects. The first involves opening for the first time a chain of boutique Macroworld Shoppe retail stores where customers could buy Macroworld products & third-party accessories and bring in their Macroworld software equipped computers...
QUESTION 1 Physical examination technique is which the nurse uses striking of a part of the...
QUESTION 1 Physical examination technique is which the nurse uses striking of a part of the body with short, sharp taps of the fingers ___________ A) Percussion. B) Palpation. C) Auscultation. D) Inspection. 0.5 points    QUESTION 2 All these equipment should be used in eye assessment except____________ A) Snellen eye chart B) Otoscope C) Penlight D) Opaque card or occluder 0.5 points    QUESTION 3 Common clinical features or Associated Factors with pain include all except__________ A) Skin rash,...
WACC Estimation The following table gives the balance sheet for Travellers Inn Inc. (TII), a company...
WACC Estimation The following table gives the balance sheet for Travellers Inn Inc. (TII), a company that was formed by merging a number of regional motel chains. Travellers Inn: (Millions of Dollars) Cash $ 10 Accounts payable $ 10 Accounts receivable 20 Accruals 15 Inventories 20 Short-term debt 0 Current assets $ 50 Current liabilities $ 25 Net fixed assets 50 Long-term debt 30 Preferred stock (50,000 shares) 5 Common equity Common stock (3,800,000 shares) $ 10 Retained earnings 30...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT