The PM for the web project left and you have been assigned to manage the project. The PERT for this project is 30 days and the variance is +/-5 days. There are too many activities on the critical path. The Early Start for task A on the critical path is day 5 and the Late Start is day 7, the Early Finish is day 10, and the Late Finish is on day 15. The CPI is 0.5, but the SPI is 1.2. What would you most be concerned about this project?
Variance |
||
Cost |
||
Schedule |
||
PERT |
Given that CPI = 0.5
CPI is used to measure or analyze the cost efficiency of the project. It measures how much of work is completed against the actual cost spent. If CPI <1, then the project is over the estimated budget
CPI = earned value / actual cost
Here CPI is 0.5 which is less than 1, so the project actual cost will be over the budget
Hence the cost is the most concerned aspect for the project
So Answer is Cost
SPI is measure of how well we are progressing on the project and it is a measure of schedule efficiency.
IF SPI >1, then it means that the project is ahead of schedule