Question

The PM for the web project left and you have been assigned to manage the project....

  1. The PM for the web project left and you have been assigned to manage the project. The PERT for this project is 30 days and the variance is +/-5 days. There are too many activities on the critical path. The Early Start for task A on the critical path is day 5 and the Late Start is day 7, the Early Finish is day 10, and the Late Finish is on day 15. The CPI is 0.5, but the SPI is 1.2. What would you most be concerned about this project?

    Variance

    Cost

    Schedule

    PERT

Homework Answers

Answer #1

Given that CPI = 0.5

CPI is used to measure or analyze the cost efficiency of the project. It measures how much of work is completed against the actual cost spent. If CPI <1, then the project is over the estimated budget

CPI = earned value / actual cost

Here CPI is 0.5 which is less than 1, so the project actual cost will be over the budget

Hence the cost is the most concerned aspect for the project

So Answer is Cost

SPI is measure of how well we are progressing on the project and it is a measure of schedule efficiency.

IF SPI >1, then it means that the project is ahead of schedule

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You have been assigned to manage a time-constrained project. The project absolutely must be finished by...
You have been assigned to manage a time-constrained project. The project absolutely must be finished by the customer-imposed deadline. No exceptions will be made, even if it means additional expenses must be incurred. As the project manager, you are busy developing the project schedule and budget. You notice that the demand for a particular resource, XT-002 Deconstructor, varies greatly over the course of the project. In an attempt to make an optimal project schedule, which of the following methods should...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
You are managing a project to film 5 promotional videos to be posted on youtube. Your...
You are managing a project to film 5 promotional videos to be posted on youtube. Your project has a BAC of $12,000. One of the tasks on the critcal path is to arrange filming locations. The task has a BAC of $2,000. You have confirmed 4 of the 10 locations. The task is scheduled to take 2 weeks (10 days), and it is the end of day 2. You have spent $300 so far. A) identify the tasks BAC, AC,...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine...
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine activities involved. These activities have been labeled A through I in the following table. The company is planning to finish the project in 34 weeks. Please answer the following questions. Determine the expected (estimated) duration and variance for each activity. You can round the expected duration numbers without decimals. Activity Immediate Predecessor(s) Optimistic Probable Pessimistic Expected duration Variance A -- 5 9 13 Answer...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT