Question

A quality manager asked his team to implement p control chart for a process that was...

A quality manager asked his team to implement p control chart for a process that was recently introduced. The team collected samples of size n = 100 parts hourly over a period of 30 hours and determined the proportion of nonconforming parts for each sample. The mean proportion of nonconforming parts for 30 samples turned out to be 0.025.

  1. Determine the upper and lower control limits for the p chart. (2 Points)
  2. Discuss how you will use the p Chart and what you will report to the manager. (3 Points)

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
An online clothing retailer monitors its order-filling process. Each week, the quality control manager selects a...
An online clothing retailer monitors its order-filling process. Each week, the quality control manager selects a random sample of size n = 350 orders that have been filled but have not shipped. The contents of the shipping container are checked against the items ordered by the customer (including color and size categories), and the order is categorized as defective or non-defective. A p chart is used to identify whether or not the process is in control. The graph below shows...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data show the temperature in degrees centigrade at five points in time during a manufacturing cycle. Sample x R 1 95.72 1.0 2 95.24 0.9 3 95.18 0.7 4 95.42 0.4 5 95.46 0.5 6 95.32 1.1 7 95.40 0.9 8 95.44 0.3 9 95.08 0.2 10 95.50 0.6 11 95.80 0.6 12 95.22 0.2 13 95.58 1.3 14 95.22 0.6 15 95.04 0.8 16...
HCH Manufacturing has decided to use a p-Chart with 2-sigma control limits to monitor the proportion...
HCH Manufacturing has decided to use a p-Chart with 2-sigma control limits to monitor the proportion of defective steel bars produced by their production process. The quality control manager randomly samples 250 steel bars at 12 successively selected time periods and counts the number of defective steel bars in the sample. Sample   Defects 1   7 2   10 3   14 4   8 5   9 6   11 7   9 8   9 9   14 10   11 11   7 12   8 Step 1 of...
to look at 36 weeks instead of 20 weeks. His quality improvement team provided him with...
to look at 36 weeks instead of 20 weeks. His quality improvement team provided him with the data below after an “intervention” was introduced in week 20. Calculate the upper and lower control limits and then construct a control chart. Display your chart. Question: Using the rules for detecting special causes, can you detect any special causes in this case? If so, what special causes can you detect? What does this mean? Was the intervention successful in reducing the delays?...
When a controlled process changes from 3s control to 6s control, it implies the s of...
When a controlled process changes from 3s control to 6s control, it implies the s of the parameter remains the same. the distance between USL-LSL becomes smaller the distance between UCL-LCL becomes smaller the % of reject increases none of the above is true In a simple linear regression analysis, the following sum of squares are produced:    The proportion of the variation in y that is explained by the variation in x is: 20% 80% 25% 50% none of...
As a member of a management team, you are concerned with the absenteeism among​ assistants. The...
As a member of a management team, you are concerned with the absenteeism among​ assistants. The issue has been raised by your management team, who feel they often have to perform work normally done by their assistants. To get the​ facts, absenteeism data were gathered for the last three​ weeks, which is considered a representative period for future conditions. After taking random samples of 65 personnel files each​ day, the following data were​ produced:                                                                                                                                         Day Assistants Absent Day Assistants...
GMP Case Study Scenario You are the quality control (QC) manager for a relatively new company...
GMP Case Study Scenario You are the quality control (QC) manager for a relatively new company that conducts manufacturing operations under contract to pharmaceutical companies. Your company’s facility handles rDNA protein products made in fermentation processes, followed by downstream purification steps, as well as and all testing. The facility was inspected in 2015 to local current good manufacturing practice (GMP) standards.   The ongoing contract you have with SuperPharma P/L has entered a new phase. SuperPharma are providing a second generation...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization....
BridgeRock is a major manufacturer of tires in the U.S.. The company had five manufacturing facilities...
BridgeRock is a major manufacturer of tires in the U.S.. The company had five manufacturing facilities where tires were made and another 20 facilities for various components and materials used in tires. Each manufacturing facility produced 10,000 tires every hour. Quality had always been emphasized at BridgeRock, but lately quality was a bigger issue because of recent fatal accidents involving tires made by other manufacturers due to tread separation. All tire manufacturers were under pressure to ensure problems did not...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT