Question

Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time...

  1. Do the following crashing problem “from scratch”

  1. Develop the time reduction and cost per unit time columns in the table. Units: Time is in days, cost is in $.

Activity

Immediate predecessor(s)

Time

Cost

Crash Time

Crash Cost

Time Reduction

Cost to Crash

A

--

10

5000

10

5000

B

A

12

1200

11

1300

C

A

11

3600

9

4800

D

B

5

300

4

600

E

C

8

1000

6

2000

F

E

9

2400

7

5400

G

D, F

8

700

7

1000

YOU HAVE A NEW DEADLINE OF 39 DAYS TO COMPLETE THE PROJECT.

Show your work for at least the first two cells in each column

  1. What are the DVs ? (remember NUN!)
  1. What is the objective function? Use dimensional analysis for at least the first two summands.
  1. On the next page, draw the network diagram, filling in the appropriate values for activity times  and earliest start and finish as done in class.  Please keep in portrait mode for Canvas grading
  1. Write the constraints below.
  1. Run the program in solver. Include your excel file with the solver setup and solution.
  2. What is the minimum cost?

  1. By how much time is each task reduced?
  1. What is the total project time?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT