Activity |
Immediate predecessor(s) |
Time |
Cost |
Crash Time |
Crash Cost |
Time Reduction |
Cost to Crash |
A |
-- |
10 |
5000 |
10 |
5000 |
||
B |
A |
12 |
1200 |
11 |
1300 |
||
C |
A |
11 |
3600 |
9 |
4800 |
||
D |
B |
5 |
300 |
4 |
600 |
||
E |
C |
8 |
1000 |
6 |
2000 |
||
F |
E |
9 |
2400 |
7 |
5400 |
||
G |
D, F |
8 |
700 |
7 |
1000 |
YOU HAVE A NEW DEADLINE OF 39 DAYS TO COMPLETE THE PROJECT.
Show your work for at least the first two cells in each column