In a hotel renovation project, some air ducts and furnaces for the new centralized air conditioning system are required. The material cost is USD 250,000. Transportation cost is USD 3,850. Administrative (order) cost is USD 1,000. A nearby storage area is available and can be rented for a cost of 65 cents/cu yd/day (knowing that the purchased material will take 2,500 cubic yards of storage). For every day of project delay, the contractor is charged a fine of USD 1,800. The activity of installing the materials has an Early Start and Late Start of 95 and 99 respectively. The probabilities of delivery for the materials are shown in the table below.
t (days) |
P(t) |
15 |
0.07 |
16 |
0.10 |
17 |
0.18 |
18 |
0.20 |
19 |
0.25 |
20 |
0.15 |
21 |
0.05 |
Calculate:
A. Expected delivery time is
15*0.07+16*0.1+17*0.18+18*0.2+19*.25+20*0.15+21*0.05= 18.11 days
B. Total costs in case material arrives at day 97
=250,000+3,850+1000+2500*0.65 = USD 256,475
Assuming the activity of installation for a normal start is 97 days ((95+99)/2)
C. Total costs in case material arrives at 102 day
=250,000+3,850+1000+2500*0.65+1800*5= USD 265,475
D. (1-.07-.1-.18)=0.65
E. Expected days = 77+18.11=95.11
Extra days = 97-95.11=1.89 equivalent to 2
If arrived on 92 day 0.07+0.1+0.18=0.35