Question

Question 142 pts In a time-series forecast, forecast error is the difference between The actual value...

Question 142 pts

In a time-series forecast, forecast error is the difference between

The actual value and the associated forecast value

The average value and the expected value of the response variable

Residual and the average value

The explanatory variable value and the response variable value

Homework Answers

Answer #1

we know that the residual is difference between the actual value and the predicted value

Similarly, the forecast error is also residual, but it is for time series

So, forecast error in the time series forecast is the difference between the actual value and the associated forecast value or predicted value

therefore, option A is correct

option B is incorrect because we never use average value for forecast error

option C is incorrect because residual is the forecast error

option D is incorrect difference between explanatory and response variable is not forecast

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Question 12 The constant difference (higher or lower) between actual demand and forecast demand is called...
Question 12 The constant difference (higher or lower) between actual demand and forecast demand is called what? It can also be found using the running sum of the forecasting error and the mean forecast error. Group of answer choices error magnitude mean absolute percent error bias Question 13 How much the forecast deviates from the actual observations is called what? It can be found by using MAPE and SDFE. Group of answer choices error running sum of the forecasting error...
1. Using the data below, what is the value of RMSE? Week Time Series Value Forecast...
1. Using the data below, what is the value of RMSE? Week Time Series Value Forecast 1 3 7.00 2 5 4.00 3 2 5.00 4 8 8.00 2. Using the data below, calculate the squared error for the 4th week. Use the 2 period moving average to create the forecast. Week Time Series Value 1 19.00 2 11.00 3 22.00 4 7.00 Please, do the all the work and show processes
In Ordinary Least Squares Regression, the gap between the value of the dependent variable and the...
In Ordinary Least Squares Regression, the gap between the value of the dependent variable and the predicted value is called Question 2 options: A) the minimizing coefficient. B) the residual. C) the error term. D) the explanatory variable.
Using a three-month moving average, the forecast value for November in the following time series is...
Using a three-month moving average, the forecast value for November in the following time series is ____________. July 5 Aug 11 Sept 13 Oct 6 a. 11.60 b. 10.00 c. 9.67 d. 8.60
Consider the following time series data. Month 1 2 3 4 5 6 7 Value 24...
Consider the following time series data. Month 1 2 3 4 5 6 7 Value 24 13 18 12 18 23 15 b. Develop the three-month moving average forecasts for this time series. Compute MSE and a forecast for month 8 (to 2 decimals if necessary). Enter negative values as negative number. Month Time Series Value Forecast Forecast Error Squared Forecast Error 1 24 2 13 3 18 4 12 ? ? ? 5 18 ? ? ? 6 23...
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 14...
Consider the following time series data. Week 1 2 3 4 5 6 Value 18 14 16 12 17 14 Using the naive method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. Round the intermediate calculations to two decimal places. Mean absolute error (to 1 decimal). Mean squared error (to 1 decimal). Mean absolute percentage error (to 2 decimals). % What is the forecast for week 7 (to the nearest whole...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 13...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 13 16 11 17 15 Using the average of all the historical data as a forecast for the next period, compute the following measures of forecast accuracy. Round your answers to two decimal places. a. Mean absolute error. b. Mean squared error. c. Mean absolute percentage error. % d. What is the forecast for week 7?
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14...
Consider the following time series data. Week 1 2 3 4 5 6 Value 19 14 17 12 18 15 Using the average of all the historical data as a forecast for the next period, compute the following measures of forecast accuracy. Round your answers to two decimal places. a. Mean absolute error. b. Mean squared error. c. Mean absolute percentage error. d. What is the forecast for week ?
Consider the following time series data. Month 1 2 3 4 5 6 7 Value 22...
Consider the following time series data. Month 1 2 3 4 5 6 7 Value 22 14 20 11 20 22 14 Round your answers to two decimal places. a. Compute MSE using the most recent value as the forecast for the next period. Mean squared error is What is the forecast for month 8? b. Compute MSE using the average of all data available as the forecast for the next period. Mean squared error is What is the forecast...
Consider the following time series data. Month 1 2 3 4 5 6 7 Value 21...
Consider the following time series data. Month 1 2 3 4 5 6 7 Value 21 10 20 11 20 23 16 Round your answers to two decimal places. a. Compute MSE using the most recent value as the forecast for the next period. Mean squared error is ________ What is the forecast for month 8?_______ b. Compute MSE using the average of all data available as the forecast for the next period. Mean squared error is ________ What is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT