Consider two processes A and B each with sample size of n = 5

           Process A: Mean = 100        Sample Standard deviation = 3

           Process B: Mean = 105        Sample Standard deviation = 1

                       Specifications are 100 + or -10,

  1. Find the process standard deviations
  2. Calculate Cp and Cpk for each process and interpret these ratios
  3. Find the percentage of production outside the specification limits
  4. Which process would you prefer?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Cp and Cpk Consider two processes A and B each with sample size of n =...
Cp and Cpk Consider two processes A and B each with sample size of n = 5 Process A: Mean = 100 and Standard deviation = 3 Process B: Mean = 105 and Standard deviation =1 Specifications are 100 +/- 10, a) Calculate Cp and Cpk for each process (show steps) b) Interpret these ratios
A process in control has an estimated standard deviation of 2 mm. The product produced by...
A process in control has an estimated standard deviation of 2 mm. The product produced by this process has specification limits of 120 ± 8 mm and a target value of 120 mm. Calculate the process capability indices Cp and Cpk for the process if the process mean shifts from 118 mm first to 122 mm and then to 124 mm, but the process variability remains the same. What will be the yield of the process for each of three...
For each of the following processes, a sample of size 400 is collected in order to...
For each of the following processes, a sample of size 400 is collected in order to estimate the process mean and variability. Process Mean Sample Standard Deviation (s or σ) Lower Spec Upper Spec A 29.3 0.74 26.8 31.8 B 119.6 2.56 115.5 132.5 Indicate which measure of process capability (Cpvs.Cpk) appears the more appropriate to use for each process, and state why. Compute the appropriate measure of process capability for each process.
The specification limits for the width of a part produced in a new machine is 3...
The specification limits for the width of a part produced in a new machine is 3 ? 0.008 centimeters. The standard deviation of the process is estimated to be 0.003 centimeters. a. What is the value of process capability index (Cp) for this process? (2 points) b. What percentage of the parts would be outside the specifications for the width of the part if the process were operated and centered at 3.000 centimeters? Assume normal distribution of measurements. (4 points)
A pharmaceutical company producing vitamin capsules desires a proportion of calcium content between 40 and 55...
A pharmaceutical company producing vitamin capsules desires a proportion of calcium content between 40 and 55 ppm. A random sample of 20 capsules chosen from the output yields a sample mean calcium content of 44 ppm with a standard deviation of 3 ppm. Find the natural tolerance limits of the process. If the process is in control at the present values of its parameters what proportion of the output will be nonconforming, assuming a normal distribution of the characteristic? Calculate...
Aspen Plastics produces plastic bottles to customer order. To monitor the process, statistical process control charts...
Aspen Plastics produces plastic bottles to customer order. To monitor the process, statistical process control charts are used. The central line of the chart for the sample means is set at 8.50 and the range at 0.31in. Assume that the sample size is 6 and the specification for the bottle neck diameter is 8.50 ± 0.25. a. Calculate the control limits for the mean and range charts. (3 points) b. Suppose that the standard deviation of the process distribution is...
A new process is started, and the sum of the sample standard deviation, ∑s, for 25...
A new process is started, and the sum of the sample standard deviation, ∑s, for 25 rows of measurement, each of subgroup size 4, is 750. If the specifications are 700 ± 80 and the process center, Xbar-bar = 720, compute (to 3 decimal places) the Process Capability Index Cpk. (Please show all work)
Broody Plastics produces plastic bottles for the customer orders. Statistical process control charts is being used...
Broody Plastics produces plastic bottles for the customer orders. Statistical process control charts is being used to monitor all the process. assume that the sample size is 4 and the specification for the bottle neck diameter is 6.00+-0.35. (Note that the central line of chart for the sample means is set at 6.00 and the range at 0.4 in.) (a) Calculate control limits for the mean and range charts. (b) If the firm is looking for the three-sigma performance, is...
Assume a population of 2, 5 and 9. Assume that samples of size n = 2...
Assume a population of 2, 5 and 9. Assume that samples of size n = 2 are randomly selected with replacement from the population. Listed below are the nine different samples. Complete parts through d below. 4,4      4,5    4,9 5,4 5,5     5,9     9,4     9,5    9,9 A.) Find the value of the population standard deviation B.) Find the standard deviation of each of the nine samples, then summarize the sampling distribution of the standard deviations in the format of a table...
Consider a sampling distribution with p equals 0.13p=0.13 and samples of size n each. Using the...
Consider a sampling distribution with p equals 0.13p=0.13 and samples of size n each. Using the appropriate​ formulas, find the mean and the standard deviation of the sampling distribution of the sample proportion. a. For a random sample of size n=5000. The standard deviation is ____ (Round to four decimal places as needed) b. For a random sample of size n=1000. The standard deviation is ____ (Round to four decimal places as needed) c. For a random sample of size...