Question

Your project has a total budget of $10,000,000. At the end of week 26 of your...

Your project has a total budget of $10,000,000. At the end of week 26 of your project, you have the following values:

  • Planned Value: $1,000,000
  • Earned Value: $750,000
  • Actual Cost: $1,250,000

Questions:

  1. What is your schedule variance?
  2. Is your project ahead of or behind schedule?
  3. What is your cost variance?
  4. Is your project over budget or under budget?
  5. Provide two estimates of the cost at completion for your project. Be sure to show your calculations.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000. Compute the following for the project (10 points) a) Cost variance. b) Schedule variance. c) If rest of the project is assumed...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
You got a contract to produce 1000 widgets for the US government. Your initial budget indicated...
You got a contract to produce 1000 widgets for the US government. Your initial budget indicated you would produce 200 widgets a week at a cost of $10/widget. You are required to use the Earned Value Method for progress reports. After 1 week you produced 250 widgets at an actual cost of $2300. What Cost Variance, Schedule Variance and Estimate at Completion will you report?
You are a project manager for a small construction project. Your project was budgeted for U.S....
You are a project manager for a small construction project. Your project was budgeted for U.S. $82,000 over a six-week period. As of today, you have spent U.S. $32,000. The earned value is U.S. $34,000. According to your schedule, you should have spent U.S. $40,000 by this time. Based on these circumstances, your project could be BEST described as: A.) Ahead of schedule B.) Behind schedule C.) On schedule D.) Not enough information is provided
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
At the end of week 24, the project with the data presented in the table below...
At the end of week 24, the project with the data presented in the table below has the earned value right on schedule, but the actual expenses are $9,000. What are the CPI, SPI, CR, ETC, and EAC? Activity Predecessors Duration (weeks) Budget ($) a - 6 900 b - 6 1200 c a 6 1200 d a 12 1800 e b, c 14 1400 f B,c,d 10 1500 g D,e 16 800
When looking at the life of a project plan, it is useful to graph and outline...
When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. Execise#2: 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the following schedule and cost estimate. What is the budget at completion (BAC) for Ralph’s garage? At the end of week 1, the contractor completed 80% of the footing, framing, and siding. He spent 3,000 on concrete, lumber and vinyl siding. He also paid 1,500 in wages to laborers to complete the footing, framing, and siding. what is the earned value (EV) for Task A...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT