1. A job is expected to have a learning curve of 90 percent. The third unit required 16 hours. The 12 th unit should take approximately how many hours?
2. Unit times for a job exhibit a learning effect. If the second unit took 30 hours, and the fourth unit took 21 hours, roughly how many hours would you estimate the third unit took?
1)for learinng rate r=0.90
here time for fist unit =T1=Tn/(n)log(r)/log(2) =16/(3)log(0.9)/log(2) =18.9079
hence time for 12th unit =T12=T1*(n)log(r)/log(2) =18.9079*(12)log(0.9)/log(2) =12.96 Hours
2)
here time for 2nd unit T2 =T1*(2)log(r)/log(2) =30 ........(1)
time for 4th unit T4=T1*(4)log(r)/log(2) =21 .........(2)
dividing 1 and 2; and solving
learning rate r=0.7
putting it in equation (1)
T1=42.8571
hence time it took to make 3rd unit =42.8571*(3)log(0.7)/log(2)=24.35 Hours