The ABC company wants to choose between two new processes, B and C. The fixed cost for process B is $40,000 and for process C, $25,000. The variable cost for B is $3.00 per unit and for C, $8.00 per unit. The two processes have the same total costs at the following:
a. 3,000 units and the total cost of $49,000. |
||
b. 3,000 units and the total cost of $15,000. |
||
c.15,000 units and the total cost of $3,000. |
||
d. 49,000 units and the total cost of $3,000. |
||
e. none of the above. |
Given that there are two processes B & C.
Let, X be the total number of units produced.
For process B
Fixed cost = $40,000
Variable cost = $3.00 per unit
Therefore, Total cost = 3X + 40000
For process C
Fixed cost = $25,000
Variable cost = $8.00 per unit
Therefore, Total cost = 8X + 25000
To find the value of X at which the two processes have same total cost.
Therefore,
Total cost of B = Total cost of C
=> 3X + 40000 = 8X + 25000
=> 40000-25000 = 8X-3X
=> 15000 = 5X
=> X= 3000
Therefore, the processes will have same total costs when they produce 3000 units and the total cost is = 3X + 40000 = 3*3000 + 40000 = 49000
Therefore, correct answer is : (a) 3,000 units and the total cost of $49,000.
** If you found my answer helpful, kindly give a positive rating. Thank you.
Get Answers For Free
Most questions answered within 1 hours.