joe studied his control chart and notice it had been built with repeated samples if 10...

joe studied his control chart and notice it had been built with repeated samples if 10 units and three sigma limits that were ucl 109.0125 and lcl 90.9875 what is process stardard vdeviation? 9.5 6.7

Homework Answers

Answer #1

confidence interval is                  
lower limit =    90.9875              
upper limit=   109.0125              

margin of error = (upper limit-lower limit)/2= (   109.0125   -   90.9875   ) / 2 =   9.0125

margin of error ,E = 3*σ/√n = 9.0125

σ = 9.0125*√10 /3 = 9.5 (answer)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A fraction nonconforming control chart with n = 400 has the following parameters: UCL = 0.0962,...
A fraction nonconforming control chart with n = 400 has the following parameters: UCL = 0.0962, Center line = 0.0500, LCL = 0.0038 a. Find the width of the control limits in standard deviation units. b. Suppose the process fraction nonconforming shifts to 0.15. What is the probability of detecting the shift on the first subsequent sample?
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data show the temperature in degrees centigrade at five points in time during a manufacturing cycle. Sample x R 1 95.72 1.0 2 95.24 0.9 3 95.18 0.7 4 95.42 0.4 5 95.46 0.5 6 95.32 1.1 7 95.40 0.9 8 95.44 0.3 9 95.08 0.2 10 95.50 0.6 11 95.80 0.6 12 95.22 0.2 13 95.58 1.3 14 95.22 0.6 15 95.04 0.8 16...
Twenty-five samples of 100 items each were inspected when a process was considered to be operating...
Twenty-five samples of 100 items each were inspected when a process was considered to be operating satisfactorily. In the 25 samples, a total of 185 items were found to be defective. (a) What is an estimate of the proportion defective when the process is in control? (b) What is the standard error of the proportion if samples of size 100 will be used for statistical process control? (Round your answer to four decimal places.) (c) Compute the upper and lower...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 0 2 15 2 3 15 0 4 15 3 5 15 1 6 15 3 7 15 1 8 15 0 9 15 0 10 15 0 a. Determine the p−p−, Sp, UCL and LCL...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 2 2 15 2 3 15 2 4 15 0 5 15 2 6 15 1 7 15 3 8 15 2 9 15 1 10 15 3 a. Determine the p−p− , Sp, UCL and...
Twelve​ samples, each containing five​ parts, were taken from a process that produces steel rods at...
Twelve​ samples, each containing five​ parts, were taken from a process that produces steel rods at Emmanual​ Kodzi's factory. The length of each rod in the samples was determined. The results were tabulated and sample means and ranges were computed. Refer to Table S6.1 - Factors for computing control chart limits (3 sigma) for this problem. Sample ​Size, n Mean​ Factor, A2 Upper​ Range, D4 Lower​ Range, D3 2 1.880 3.268 0 3 1.023 2.574 0 4 0.729 2.282 0...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 0 2 15 0 3 15 0 4 15 2 5 15 0 6 15 3 7 15 1 8 15 0 9 15 3 10 15 1 a. Determine the p−p−, Sp, UCL and LCL...
A control chart for fraction nonconforming indicates that the current process average is 0.03. The sample...
A control chart for fraction nonconforming indicates that the current process average is 0.03. The sample size is constant at 200 units. a) Find the three-sigma control limits for the control chart. b) What is the probability that a shift in the process average to 0.08 will be detected on the first subsequent sample? (Hint: use normal approximation) c) What is the probability that this shift will be detected on the second sample taken after the shift?
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 1 2 15 1 3 15 3 4 15 1 5 15 0 6 15 0 7 15 2 8 15 1 9 15 2 10 15 1 a. Determine the p−p− , Sp, UCL and...
A quality manager asked his team to implement p control chart for a process that was...
A quality manager asked his team to implement p control chart for a process that was recently introduced. The team collected samples of size n = 100 parts hourly over a period of 30 hours and determined the proportion of nonconforming parts for each sample. The mean proportion of nonconforming parts for 30 samples turned out to be 0.025. Determine the upper and lower control limits for the p chart. (2 Points) Discuss how you will use the p Chart...