Question

The Three Hills Power Company provides electricity to a large metropolitan area through a series of...

The Three Hills Power Company provides electricity to a large metropolitan area through a series of almost 200 hydroelectric generators. Management recognizes that even a well-maintained generator will have periodic failures or breakdowns. Energy demands over the past three years have been consistently high and the company is concerned over downtime of generators. It currently employs 4 highly skilled and highly paid ($30 per hour) repairpersons. Each works every fourth 8-hour shift, so there is a repairperson on duty 24 hours a day, seven days a week.

     Breakdown expenses are also very costly. For each hour that one of its generators is down, Three Hills loses approximately $75. This amount is the charge for reserve power that Three Hills must “borrow” from the neighboring utility company.

     Stephanie Robbins has been assigned to simulate maintenance costs. Her objective is to determine the total cost of the system made up of 1) the service maintenance cost and 2) the machine breakdown cost. The time between successive generator breakdowns varies from one-half hour to 3 hours, and is shown in Table 1 below along with the frequency of each time occurring across 100 breakdowns.

Question 1: Fill out below (table 1)

Table 1
Time between machine failures (hours) Number of times observed (frequency) Probability Cumulative Probability Random Number Interval
0.5 5
1.0 6
1.5 16
2.0 33
2.5 21
3.0 19
Total 100
Table 2
Repair Time Required (hours) Probability
1 0.28
2 0.52
3 0.20
Total 1.00

Question 2: Complete a simulation of this scenario for 10 generator breakdowns in the table on the next page. You can assume that there is only one repairperson working at a time and that each repairperson works only an 8-hour shift. Thus, when each person is replaced by the next shift, he or she just hands the tools over to the next worker who continues working on the same generator until the job is completed. Also assume that you are starting the analysis at midnight (time 00:00). Table 2 below shows the required repair time.

one repairperson:

Breakdown Number

RN for Breakdowns

Time between breakdowns

Time of breakdown

Time repairperson is free to begin repair

RN for Repair Time

Repair time required

Time Repair ends

Number of Hours Machine Down

1

.57

.07

2

.17

.60

3

.36

.77

4

.72

.49

5

.85

.76

6

.31

.95

7

.44

.51

8

.30

.16

9

.26

.14

10

.09

.85

Homework Answers

Answer #1

Sol:

Q1).

The total cost of the system is $208.

If you Satisfy with Answer, Please give me "Thumb Up". It was very important to me.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Three Hills Power Company provides electricity to a large metropolitan area through a series of...
The Three Hills Power Company provides electricity to a large metropolitan area through a series of almost 200 hydroelectric generators. Management recognizes that even a well-maintained generator will have periodic failures or breakdowns. Energy demands over the past three years have been consistently high and the company is concerned over downtime of generators. It currently employs 4 highly skilled and highly paid ($30 per hour) repairpersons. Each works every fourth 8-hour shift, so there is a repairperson on duty 24...
One of the large photocopiers used by a printing company has a number of special functions...
One of the large photocopiers used by a printing company has a number of special functions unique to that particular model. This photocopier generally performs well but, because of the complexity of its design and the frequency of usage, it occasionally breaks down. The department has kept records of the number of breakdowns per month over the last fifty months. The data is summarized in the table below:    Number of Breakdowns Probability 0 0.12 1 0.32 2 0.24 3...
One of the large photocopiers used by a printing company has a number of special functions...
One of the large photocopiers used by a printing company has a number of special functions unique to that particular model. This photocopier generally performs well but, because of the complexity of its design and the frequency of usage, it occasionally breaks down. The department has kept records of the number of breakdowns per month over the last fifty months. The data is summarized in the table below:    Number of Breakdowns Probability 0 0.12 1 0.32 2 0.24 3...
A manufacturing facility has a repair shop with two repairmen who repair failed machines on a...
A manufacturing facility has a repair shop with two repairmen who repair failed machines on a first-fail-first-serve basis. They work together on the machine if there is one machine down (the repair still takes the same amount of time), and otherwise, each works on a separate machine. Thus, if there are more than two machines down, new failures simply wait for their turn to be repaired. Assume that machine failures arrive in a combined failure stream, so that we do...
please post solutions using R a manufacturing facility has a repair shop with two repairmen who...
please post solutions using R a manufacturing facility has a repair shop with two repairmen who repair failed machines on a first-fail-first-serve basis. They work together on the machine if there is one machine down (the repair still takes the same amount of time), and otherwise, each works on a separate machine. Thus, if there are more than two machines down, new failures simply wait for their turn to be repaired. Assume that machine failures arrive in a combined failure...
1. Johnson Filtration, Inc., provides maintenance service for water-filtration systems throughout southern Florida. Customers contact Johnson...
1. Johnson Filtration, Inc., provides maintenance service for water-filtration systems throughout southern Florida. Customers contact Johnson with requests for maintenance service on their water-filtration systems. To estimate the service time and the service cost, Johnson’s managers want to predict the repair time necessary for each maintenance request. Management collected data over the last 10 service calls, and ran a multiple regression analysis on this sample. As a result, they developed the following estimated regression equation to predict y = the...
The table below shows the forecast for Company X over the next four quarters. Management has...
The table below shows the forecast for Company X over the next four quarters. Management has decided to use a level capacity strategy with 20 employees. The company works 1 eight hour shift a day, and workers are given 2 paid 15 minute breaks. It takes 2 hours to make a unit and the company works 60 days in a quarter. What would be the production plan in every quarter under this plan? (Round any fractional output to the nearest...
Q1d08A.) Edward Shack is conducting a simulation of a serial production line for Lowliner Foods in...
Q1d08A.) Edward Shack is conducting a simulation of a serial production line for Lowliner Foods in St John’s, NL. The line processes fresh fish into frozen fish fingers. The line operates on three shift basis, 7.5 hours per shift, with a half-hour between shifts. Machines are idled between the shifts. a.) Mr. Shack is very interested in determining the effect of unscheduled downtime of the flash freezing unit on shift output. Eddie has implemented a data collection procedure that will...
Johnny Thompson's poster company works on 3 types of printing jobs, each of which could be...
Johnny Thompson's poster company works on 3 types of printing jobs, each of which could be produced on the same model machine. The predicted annual demands and typical order sizes are shown in the table below. The company has 2000 production hours available each year and requires a 10% capacity cushion to allow for preventive maintenance, breakdowns, and other unforeseen circumstances. How many printing machines must they have under these circumstances? Show all of your work. Job Type Job A...
3. The Dynaco Manufacturing Company produces a product in a process consisting of operations of five...
3. The Dynaco Manufacturing Company produces a product in a process consisting of operations of five machines. The probability distribution of the number of machines that will break down in a week follows: Machine Breakdowns Per Week   Probability 0 0.10 1 0.20 2 0.15 3 0.30 4 0.15 5 0.10 1.00 a. Simulate the machine breakdowns per week for 20 weeks. b. Compute the average number of machines that will break down per week. 4. Simulate the following decision situation...