Question

DONLEY BROTHERS The Donley Brothers Company had encountered the problem of latent defects in some of...

DONLEY BROTHERS

The Donley Brothers Company had encountered the problem of latent defects in some of its purchased castings. Being latent, the defects did not show up until after machining had taken place at Donley

Brothers. This group of failures greatly irritated the manufacturing boss, who declared that “repairing

those darn castings is eating up all our profits.”

When the defects were discovered, the rough casting had to be taken off the machine, the defect

chipped out and repair-welded, and the casting remachined when possible. Even with this process, almost

12 percent of the incoming castings ended up as scrap. Actually, 1,140 raw castings had to be purchased

and machined in order to produce 1,000 good machined ones. The raw castings cost $600 each from

either of two suppliers. Worse than the costs associated with rework and high scrap rates were the

continual changes in production scheduling necessitated by a machined casting not being available as

scheduled. These changes were costly because they required shop personnel to tear down the job they

were working on and set up a new job. Marketing was constantly complaining about the firm’s inability

to meet delivery commitments for the finished machinery that incorporated the castings. Marketing

claimed that many sales were lost as a result of this failure.

George Donley, the production manager, and Terry Donley, the vice president for marketing,

asked Bob Donley, the supply manager, to investigate the costs involved in supplying finished machined

castings. If finished castings were purchased, the responsibility for finding hidden defects would be that

of the supplier. Such action would encourage the supplier to improve the casting quality. Donley Brothers would accept and pay only for finished, usable castings.

The internal cost of machining each incoming rough casting and repair-welding and remachining

it, as necessary, was approximately $312 per casting. This figure included $156 of direct labor and $156

of overhead. The accounting department estimated that overhead, which was 100 percent of direct labor,

consisted of 50 percent variable and 50 percent fixed costs. No estimate was available on the cost of

disrupted production schedules and operations.

Bob approached all his major suppliers of castings in an attempt to generate interest for the

supply of finished machined castings. Only one supplier, Akron Foundry, showed genuine interest. Of

major concern to all the foundries was the $120,000 to $160,000 investment necessary to set themselves

up to machine the raw castings. Akron was willing both to invest in the necessary machines and to

guarantee delivery of up to 150 units per month—provided Donley Brothers would contract with it as a

sole source for the castings for the next three years. The price per casting would be $1,000 the first year,

with an annual increase or decrease in price tied to an appropriate economic index.

Bob was faced with the problem of deciding whether to recommend contracting with Akron

Foundry for finished castings, continuing as in the past buying rough castings, or developing a more

attractive alternative. The Donley machine shop was currently operating at 90 percent of capacity, but it

was not possible to make a reliable estimate of what would happen in the next few months, let alone the

next three years. The decision of whether to buy finished castings was of major dollar importance to Donley Brothers because the firm used at least 1,000 finished castings per year and anticipated that this

usage would continue for each of the next five years.

1. In the Donley Brothers case (reprinted later in this exam) that we studied, let’s say that we could purchase an inspection process that is able to screen the incoming rough castings to find the latent defective castings and send only the good castings to machining. This inspection is 100% reliable; i.e., it always finds the defective castings, and never is in error. Unfortunately, the contract with our suppliers does not allow us to send back the defective castings for credit; we still have to buy 1140 castings to get the 1000 good ones. We will, however, only have to machine good castings. Since we would now only have to machine good castings, the cost accountants recalculated the cost under this new situation; the new costs would be direct labor of $100 per unit, plus overhead of 167% of direct labor (of which $78 per unit is variable overhead and the rest is fixed). These costs only apply to this situation where we are machining only good castings.

Assume that we still have the reject rate for rough castings as discussed in the case and we will not purchase the machined castings from Akron. Assume that other costs that cannot be determined, such as disruption and lost sales costs, will not be factored into this analysis. Assume that the annual demand will be 1000 good machined castings per year (as was discussed in the case).

      What is the maximum annual amount that you would be willing to pay for the inspection process? Justify this amount and provide your numerical analysis.

Homework Answers

Answer #1

Donley case:

Cost to make 1000 good machined castings per year is -

Raw material casting = $600 * 1140 = 684,000

Labor = $156 * 1140 = $177,840

Overhead = $156 * 1140 = $177,840

Total = raw material casting + labor + overheads

= 684,000 + 177,840 + 177,840 = $1,039,680

Cost to purchase 1000 finished castings = 1000 * $1000 = $1,000,000

Annual variable cost = $600 * 1140 = $684,000

Labor = $156 * 1140 = $177,840

Variable overhead = $78 * 1140 = $88,920

Total = $684,000 + 177,840 + 88,920 = $950,760

Contribution to overheads = $1,000,000 - $950,760 = $49,240

Inspection is 100% reliable.

So, the maximum amount that would be willing to pay for the inspection process is - $49,240 which is also an overhead cost.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem 20-2A The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing...
Problem 20-2A The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit...
Problem 20-2A The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing...
Problem 20-2A The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit...
Collini Corporation has two production departments, Machining and Customizing. The company uses a job-order costing system...
Collini Corporation has two production departments, Machining and Customizing. The company uses a job-order costing system and computes a predetermined overhead rate in each production department. The Machining Department’s predetermined overhead rate is based on machine-hours and the Customizing Department’s predetermined overhead rate is based on direct labor-hours. At the beginning of the current year, the company had made the following estimates: Machining Customizing Machine-hours 17,000 15,000 Direct labor-hours 3,000 6,000 Total fixed manufacturing overhead cost $ 102,000 $ 61,200...
Problem 7-2A a-c (Video) The management of Shatner Manufacturing Company is trying to decide whether to...
Problem 7-2A a-c (Video) The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each...
Internal and External Linkages, Strategic Cost Management Maxwell Company produces a variety of kitchen appliances, including...
Internal and External Linkages, Strategic Cost Management Maxwell Company produces a variety of kitchen appliances, including cooking ranges and dishwashers. Over the past several years, competition has intensified. In order to maintain—and perhaps increase—its market share, Maxwell’s management decided that the overall quality of its products had to be increased. Furthermore, costs needed to be reduced so that the selling prices of its products could be reduced. After some investigation, Maxwell concluded that many of its problems could be traced...
We constantly seem to be pricing ourselves out of some markets and not charging enough in...
We constantly seem to be pricing ourselves out of some markets and not charging enough in others. Our pricing policy is pretty simple: we mark up our full manufacturing cost by 50%. That means a computer that costs us $2,000 to manufacture will sell for $3,000. Until now I thought this was a workable approach, but now I’m not so sure. Steve Works, CEO, Cortland Manufacturing, Inc. (CMI) Steve’s Controller, Sally Nomer, had just told him that she believed the...
Assignment Description Madina Electrical Corporation manufactures electric motors for commercial use. The company produces three models...
Assignment Description Madina Electrical Corporation manufactures electric motors for commercial use. The company produces three models called SM, DM and HDM. The company uses a job costing system with manufacturing overhead applied on the basis of direct labour hours. The system has been in place with little change for 30 years. Product costs and annual sales data are as follows: SM DM HDM Annual sales (units) 42500 1700 20000 Product costs: Raw material $27.50 $47.75 $73.00 Direct labour $20.00 $35.00...
We constantly seem to be pricing ourselves out of some markets and not charging enough in...
We constantly seem to be pricing ourselves out of some markets and not charging enough in others. Our pricing policy is pretty simple: we mark up our full manufacturing cost by 50%. That means a computer that costs us $2,000 to manufacture will sell for $3,000. Until now I thought this was a workable approach, but now I’m not so sure. Steve Works, CEO, Cortland Manufacturing, Inc. (CMI) Steve’s Controller, Sally Nomer, had just told him that she believed the...
Case Study 7-2 FIVE STAR TOOLS Five star tools is a small family -owned firm that...
Case Study 7-2 FIVE STAR TOOLS Five star tools is a small family -owned firm that manufactures diamond -coated cutting tools( chisels and saws) used by jewelers. Production involves three major processes. First, steel “ blanks” (tools without the diamond coating) are cut to size. Second, the blanks are sent to a chemical bath that prepares the tools for the coating process. In the third major process, the blanks are coated with diamond chips in a proprietary process that simultaneously...
Cascade Seating Inc. is a large manufacturer of automobile seat covers. Jan Davis, the controller just...
Cascade Seating Inc. is a large manufacturer of automobile seat covers. Jan Davis, the controller just received a disturbing call from the plant manager, Dave Garcia. General Motors had just downgraded Cascade from preferred supplier to backup supplier. GM cited the inconsistent fit of the seat covers as the reason, and suggested to Dave that he read an article “How Velcro Got Hooked on Quality.”9 GM had downgraded Velcro a few years back in a similar fashion, but Velcro had...