Question

Estimated durations are provided for four types of activity Analysis Production Testing Installation Predecessors None 50%...

Estimated durations are provided for four types of activity

Analysis

Production

Testing

Installation

Predecessors

None

50% of analysis

Production

Testing

Cost per week

$7000

$15000

$8000

$3000

Crews on hand

2

3

1

1

You can split jobs, but not across crews doing the same function. (So you could do a week of analysis on A1 with Analysis Crew 1, then have them do something else, and come back later and do the other 3 weeks on A1. But you can’t have Analysis Crew 1 and Analysis Crew 2 both work on the same project.) Production can’t start until 50% of Analysis is done and you can’t finish Production until Analysis is completely done. You can hire new crews and you have to hire staff prior to using them, because there is a four week training period to indoctrinate people into your company’s way of doing things (training is paid at the full rate for that type of crew).  So therefore, starting times may have to wait for your indoctrination program unless you have hired people ahead. For those periods after the four week orientation when you do not have work for them, you can rent them out to others at a loss of $2000 per week per crew. You can lay off crews after their work is done.

Create a Gantt chart scheduling the following jobs. If you miss the deadlines there is a pentalty of $50,000 per week. The revenues are collected at the end of the week the job is completed.

Job

Analysis

Production

Testing

Installation

Due by end of

Revenue

A1

4 weeks

7 weeks

3 weeks

2 weeks

Week 20

$200,000

A2

4 weeks

6 weeks

2 weeks

2 weeks

Week 20

$210,000

A3

6 weeks

9 weeks

3 weeks

3 weeks

Week 30

$250,000

A4

8 weeks

12 weeks

5 weeks

4 weeks

Week 40

$350,000

A5

8 weeks

14 weeks

6 weeks

5 weeks

Week 40

$400,000

Create a cash flow plan for maximum profit that shows:

Weeks each crew is to work, what they are to work on, cash flow

Homework Answers

Answer #1

Here we have to preapare a cash flow plan for maximum profit

Salary for crew of analysis
A1 18 7000 0 5000 126000
A2 12 7000 0 5000 84000
Salary for crew of production
P1 30 15000 2 013000 424000
P2 23 15000 0 13000 345000
Salary for crew of testing
T1 35 8000 13 6000 202000
Salary for crew of installation
I1 39 3000 22 1000 95000
Total 1276000

Now we have prepare the revenue for project Cash flow

Total Revenue for project
A1 200000
A2 2100000
A3 250000
A4 350000
A5 400000
Total 1410000
Cash flow 134000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Critical Incident 2- Job analysis At the last meeting of managers and supervisors, a major topic...
Critical Incident 2- Job analysis At the last meeting of managers and supervisors, a major topic of discussion pertained to employee confusion regarding their job duties. Some employees refuse to do any work outside their usual routine, exclaiming, “That’s not my job!” This is somewhat understandable since the company has no written job descriptions. Job duties have been informal understandings, originating when the company began only a few years ago (when the company had few employees), and no one had...
Matthew and Mark work for AMG, and want to do some aggregate planning using "Level Production...
Matthew and Mark work for AMG, and want to do some aggregate planning using "Level Production without Backorders" for the manufacturing of brake calipers for Mercedes Benz S63 sedans. They figure the front brake calipers take 9 hours to forge and assemble while the rear calipers take 7 hours to forge and assemble. They pay their people $24.00 per hour and it costs them $900.00 to hire and $1,300 to fire each employee. They currently employ 6 people and have...
. A manufacturing company produces diesel engines in four factories located in Tucson, Seattle, Baltimore, and...
. A manufacturing company produces diesel engines in four factories located in Tucson, Seattle, Baltimore, and Detroit. Three trucking firms purchase these engines for their plants located in Nashville, Miami, and Charleston. The supplies and demands, along with the per engine transportation costs in dollars are given below:                                                                           Plant                                                               Nashville             Miami         Charleston         Supply              __________________________________________________________________                         Tucson                800               1100                400                  35    Factory            Seattle                 550               950                 600                  35                        ...
1. Suppose you have an empty garage that costs you roughly $50 per month to maintain...
1. Suppose you have an empty garage that costs you roughly $50 per month to maintain in fees related to taxes and insurance. A neighbor asks if it were possible for you to rent the garage to them for $75 per month. If you decide to not rent the garage, but rather just leave it empty what is the total cost of the garage to you? Suppose you rent the garage to the neighbor what is your net profit? 2....
Section A. Job Analysis Case Scenario 1: The following case scenario is the background that would...
Section A. Job Analysis Case Scenario 1: The following case scenario is the background that would guide your answers in Sections A. You are the Human Resources Manager at the Bahrain office of a well reputed real estate firm ‘Homes are Us’ specialized in creating, selling, and maintaining the high-end residential spaces. The company’s headquarters is in Bahrain, with other offices in Saudi Arabia, Oman & Kuwait and employs around 100 professionals. The sales team comprises of a Sales Manager,...
So, the brewery selected it’s place and now needs to hire folks. After some testing, they...
So, the brewery selected it’s place and now needs to hire folks. After some testing, they expect to have approximately 2,000 customers per week. Since they will be open 7 days a week, they need to hire people to help serve their beer. They know that Friday and Saturday will drive sales. Between these 2 days, they will get 50% of their weekly sales. So, Friday has 25% of sales and Saturday has 25% of the sales. As for Sunday...
Job Analysis Methods There are various methods for analyzing jobs. Two methods of job analysis discussed...
Job Analysis Methods There are various methods for analyzing jobs. Two methods of job analysis discussed in this section are the position analysis questionnaire (PAQ) and the Occupational Information Network (O*NET). There is no "one best way" to analyze all jobs. Managers may not have the time to use these techniques exactly as they are intended for use. However, these methods are still useful because they provide a solid foundation for thinking about different approaches to job analysis. Job analysis...
vThere are 3 steps in a laundry shop: i) Washing, ii) Drying, iii) Folding. If we...
vThere are 3 steps in a laundry shop: i) Washing, ii) Drying, iii) Folding. If we assume the time to do each load is 25, 50 and 35 minutes, respectively. We can assume that there is no variability in the process and all operations work fully efficiently. a) What is the Lead Time of the laundry shop? b) What is the Cycle Time? What is the throughput rate (loads per hour) of the laundry? c) What is the utilization %...
Activity 2: Pablo and Paige (Power in Relationships) After reading the conversations, answer the following questions:...
Activity 2: Pablo and Paige (Power in Relationships) After reading the conversations, answer the following questions: Analyze the role power plays in this relationship. Hint: think of distributive (either/or), integrative (and/both), or power denial. Identify Paige’s RICE currencies. Identify Pablo’s RICE currencies. Who occupies a higher power position and lower power position in conversation 1? Make sure to give concrete reasons to support your answer. Who occupies a higher power position and lower power position in conversation 2? Make sure...
Homework Problem 1: Andreas Drauschke and Angie Clark work comparable jobs for comparable pay at department...
Homework Problem 1: Andreas Drauschke and Angie Clark work comparable jobs for comparable pay at department stores in Berlin and suburban Washington, DC. But there is no comparison when it comes to the hours they put in. Mr. Drauschke’s job calls for a 37-hour week with 6 weeks’ annual vacation. His store closes for the weekend at 2 p.m. on Saturday afternoon and stays open one evening each week-a new service in Germany that Mr. Drauschke detests. “I can’t understand...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT