Question

Suppose that an asset generates cash flows of $100, $200, and $300 at the end of years one, two, and three, respectively. If the discount rate is 10%, which of the following answers is the only one that can be correct? [Note: Show calculations to justify the answer chosen]

a. The PV = $600, FV3 = $600.

b. PV > $600, FV3 < $600.

c. PV = $481.59, FV3 = $641.00.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
a) Suppose that an asset generates cash flows of $100, $200, and $300 at the end...
a) Suppose that an asset generates cash flows of $100, $200, and $300 at the end of years one, two, and three, respectively. If the discount rate is 10%, which of the following answers is the only one that can be correct? [Note: Show calculations to justify the answer chosen] a. The PV = $600, FV3 = $600. b. PV > $600, FV3 < $600. c. PV = $481.59, FV3 = $641.00.
A project generates a cash flow of $497,400.00 per year (end of year cash flows). If...
A project generates a cash flow of $497,400.00 per year (end of year cash flows). If the project can last 15.00 more years, what is its value TODAY of the remaining cash flows if the cost of capital is 8.00%? A real estate investment has the following expected cash flows: Year Cash Flows 1 $13,600.00 2 $27,200.00 3 $44,000.00 4 $42,700.00 The discount rate is 10.00 percent. What is the investment's future value at the end of the fourth year?
Suppose you are looking at the following possible cash flows: Year 1 CF = $500; Year...
Suppose you are looking at the following possible cash flows: Year 1 CF = $500; Year 2 CF = $300; Year 3 CF = $200; Year 4 CF = $600; The required discount rate is 5%. What is the value of the cash flows today? What is the value of the cash flows at the end of year 3? What is the value of the cash flows at the end of year 5?
Suppose a project costs $300 and produce cash flows of $100 over each of the following...
Suppose a project costs $300 and produce cash flows of $100 over each of the following six years. What is the IRR?
Given the following end-of-year cash flows, what is the implicit discount rate if the PV is...
Given the following end-of-year cash flows, what is the implicit discount rate if the PV is $2,020? Year Cash Flow 1 $500 2 $750 3 $1,000 Choose one of the following answers 4.50% 4.80% 5.00% This is correct but how do we know? 5.40%
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50...
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50 and $100, at the end of the first and second years, respectively. (There is no cash flow after the second year) The firm uses a hurdle rate of 15% for projects of similar risk. Determine whether you should accept or reject the project based on NPV. Determine whether you should accept or reject the project based on IRR. Determine whether you should accept or...
Suppose a project generates positive cash flows for the next 12 years and the project’s NPV...
Suppose a project generates positive cash flows for the next 12 years and the project’s NPV is $110,000 when discount rate is 6%. Also suppose that the IRR=8.7%. Which of the following may be a possible value for NPV when discount rate is 7.4%? A. -$25,000 B. 0 C. $25,000 D. $125,000 E. None of the above
An investment costs $465 and is expected to produce cash flows of $100 at the end...
An investment costs $465 and is expected to produce cash flows of $100 at the end of each of the next 4 years, then an extra lump sum payment of $200 at the end of the fourth year. What is the expected rate of return on this investment? Please show me how to work this problem on Excel. Thank you.
Assume that you have the following possible cash flows: Years 1 and 2 CFs = $300;...
Assume that you have the following possible cash flows: Years 1 and 2 CFs = $300; Year 3 CF = $100; Years 4 and 5 CFs = $200. What is the value of the cash flows at today if the required discount rate is 5%? A. 556.45 B. 695.45 C. 569.45 D. 956.45 E. 965.45
Tomkat Corp. has only a single asset. This asset generates operating cash flow of $200,000 per...
Tomkat Corp. has only a single asset. This asset generates operating cash flow of $200,000 per year, in perpetuity. Tomkat also has a single liability, which is a perpetual bond (the maturity date is infinitely far in the future) that has a face value of $1 million and that pays coupon interest at a rate of 8% once per year. The appropriate discount rate for all cash flows in this problem is 10% per year. (a) What is the value...