Question

COD (organic) concentration: 9 mg/L Effluent concentration required: 0.9 mg/L Ozone treatment, r= 0.048/hr a) What...

COD (organic) concentration: 9 mg/L

Effluent concentration required: 0.9 mg/L

Ozone treatment, r= 0.048/hr

a) What is the time required in the tank?

b) if Q= 1000 L/day, how large should the tank be?

Homework Answers

Answer #1

while seeing in solution u may get a doubt that rate of reaction is mentioned in the question but it has taken as rate constant....for tthat once check the units rate of rreaction units always iin the mass or mole / volume x time....But in question it mentioned that only 1/ time...that is units of rate constant for first order reaction....thank you have a nice day

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A starch wastewater contains 100 mg/L COD and after treatment by an electrochemicalreactor, the effluent COD...
A starch wastewater contains 100 mg/L COD and after treatment by an electrochemicalreactor, the effluent COD is reduced to 1 mg/L. Knowing that the treatment time is 30 min, thevolume of the reactor is 50 L, and the DC current is 20 A. Calculate the instantaneous currentefficiency (ICE)
Environmental Engineering biological processes, A wastewater with a COD concentration of 970 mg / L 8,000...
Environmental Engineering biological processes, A wastewater with a COD concentration of 970 mg / L 8,000 m3 / day flow, fully mixed back It will be treated in a cyclic activated sludge system.Treatment system mud age will be 5 days will be designed in a way. Kinetic and stoichiometric coefficients were determined as follows. Volumetric organic loading speed: 0,5 kg COD/m3.day uH : 3,7 day-1, bH: 0,04 day-1, KS: 45 mg COD/L, YH: 0,5 g VSS/g COD VSS/TSS: 0,8 mg...
6. (1) A water treatment plant applies chlorine for disinfection so that 10 mg/L chlorine is...
6. (1) A water treatment plant applies chlorine for disinfection so that 10 mg/L chlorine is achieved immediately after mixing. The volume of water treated each day is 25,000,000 gal. What is the mass of chlorine needed by this plant every day? (2) The disinfection takes place in a contact tank which is a CSTR at steady state. Chlorine concentration in the contact tank is constant at 3 mg/L. Effluent of this contact tank will enter drinking water distribution systems...
Ammonia plus organic nitrogen (mg/L) was measured in samples of precipitation, as given below. What is...
Ammonia plus organic nitrogen (mg/L) was measured in samples of precipitation, as given below. What is the best number to represent the “average” of the ammonia plus organic nitrogen concentration? and why? (Hint: Which observation might be considered an outlier? How does this affect the summary statistics used?) Ammonia plus organic nitrogen (mg/L) 0.002 0.3 0.9 0.36 0.92 0.5 1.0 0.7 9.7 0.7 1.3
ANSWER as much as possible: Design an activated sludge process consisting of a complete mix flow...
ANSWER as much as possible: Design an activated sludge process consisting of a complete mix flow through aeration tank followed by final settling tanks. The sizing of the reactor and all appurtenances should be based on a solids retention time, (SRT), of 4 days and the particulates given below. Biological characteristics: Ks = 20 mg/L COD, kd = 0.1 per day, mumax = 3 gVSS/gVSS-day,    Y = 0.4 gVSS/gCOD Primary settling Tank Effluent Characteristics: Q= 20MGD, biodegradable COD, bCOD...
The volumetric flow to the ACME wastewater treatment plant is 25 MGD. The influent soluble BOD5...
The volumetric flow to the ACME wastewater treatment plant is 25 MGD. The influent soluble BOD5 is 200 mg/L and the effluent soluble BOD5 is 8 mg/L. The plant is designed to operate with a mean cell (biomass) residence time of 10 days. The yield coefficient is 0.6 mg biomass/mg substrate, and the biomass decay rate is 0.09/day. The reactor is to operate at a biomass concentration of 2500 mg/L. The thickened underflow biomass concentration from the secondary clarifier is...
Problem #3: Biochemical Oxygen Demand (BOD) and Stream Quality A wastewater treatment plant designed for a...
Problem #3: Biochemical Oxygen Demand (BOD) and Stream Quality A wastewater treatment plant designed for a community of 45,000 people has a flow of 100 gal/person/day and a BOD5 loading of 0.2 lb/person/day. The upstream characteristics of the receiving waters are: stream flow rate = 20 cfs and BOD5 = 2 mg/L The water quality standards require the in-stream BOD5 to be less than 7 mg/L in this stretch of the river. The minimum BOD removal efficiency that the treatment...
You have been retained to design a wastewater treatment plant using a conventional activated sludge process...
You have been retained to design a wastewater treatment plant using a conventional activated sludge process for a town of 40,000 people. The industrial flow contribution to the sewer system is 300,000 gallons per day. Effluent discharge standards require effluent BOD5 and total suspended solids concentration of <10 mg/l. Assume the following design criteria are applicable: Domestic sewage flow = 100 gal/cap/day (including I/I) BOD loading = 0.18 lbs/cap/day TSS loading = 0.20 lbs/cap/day BOD removal in primary = 33%...
(b) Which is not on-site wastewater treatment system? i) Septic system ii) Pit privy iii) Absorption...
(b) Which is not on-site wastewater treatment system? i) Septic system ii) Pit privy iii) Absorption field iv) Carbonation (f) DNA alternation is caused by i) Carcinogen ii) Teratogen iii) Acetogen iv) Mutagen (g) The relationship between substrate and growth rate of aerobes can be explained by (j) If F/M is high, then i) Longer SRT ii) High yield iii) Better effluent quality iv) Microbes are starving (k) During biological P removal, PAOs i) release S in anaerobic condition ii)...
Objective: The student will apply course objectives through evaluating patient assessments, identifying treatment options and developing...
Objective: The student will apply course objectives through evaluating patient assessments, identifying treatment options and developing teaching plans for patients with obesity, peptic ulcer disease (PUD) and gastroesophageal reflux disease (GERD). Part I: Obesity & Bariatric Surgery A 32-year-old obese patient has come to the bariatric outpatient center to have an initial evaluation. The patient reports that they were always overweight, even as a child. The patient states that they are frustrated because they gained 100 pounds over the last...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT