Given the following data, develop MRP tables and indicate the Planned order releases for all items.
A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.)
Period |
6 |
7 |
8 |
GR-A |
400 |
0 |
300 |
On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for A and a lot size of 500 or multiples of 500 for C and F.
Draw the Bill of Materials Fill up the Low level code Table
Item |
Low level code |
A |
|
C |
|
F |
A |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
C |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
F |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
BEST REGARDS....