Which of the following is NOT a good reason to terminate (kill) a project?
a) Consistent budget and schedule overruns.
b) Changing organizational priorities.
c) Uncertainty regarding the project’s outcomes.
d) Wrong resources assigned to the project.
The project whose resources are wrongly assigned can be revived again by going through the process of resource management once again. Killing project for reason which could have been fixed could lead to unnecessary losses. In all other options terminating project makes sense since budget and costs overruns will make project unfeasible. Also, changing organization priority means project no longer is required for fulfilling company vision. Uncertainty regarding outcomes may make project too risky to pursue.
Therefore, correct answer is option d.