Write a scope statement based on the information below:
Analysis |
Design |
Implementation |
Collect list of 20 projects |
Gather detailed requirements for desired outputs from the database |
Enter project data |
Gather information on projects |
Create fully attributed, normalized data model |
Test database |
Define draft requirements |
Create list of edit rules for fields, determine default values, develop queries, and determine formats for reports |
Make adjustments, as needed |
Create entity relationship diagram for database |
Develop list of queries required for database |
Conduct user testing |
Create sample entry screen |
Review design information with customer |
Make adjustments based on user testing |
Create sample report |
Make adjustments to design based on customer feedback |
Create online Help, user manual, and other documentation |
Develop simple prototype of database |
Create full table structure in database prototype |
Train users on the system |
Review prototype with customer |
Create data input screens |
|
Make adjustments based on customer feedback |
Write queries |
|
Create reports |
||
Create main screen |
||
Review new prototype with customer |
The activities and tasks defined in the project plan must be undertaken within the scope of the project. For this reason, reiterate the scope of the project here as defined in the Project Charter.
Background Info:
Exercise A-4: Project Tracking Database
Expand the Project Tracking Database example. Assume that XYZ
Company wants to create a history of project information, and the
Project Tracking Database example is the best format for this type
of history. The company wants to track information on 20 past and
current projects and wants the database to be able to handle 100
projects total. The company wants to track the following project
information:
Project name
Sponsor name
Sponsor department
Type of project
Project description
Project manager
Team members
Date project was proposed
Date project was approved or denied
Initial cost estimate
Initial time estimate
Dates of milestones (e.g., project approval, funding approval,
project completion)
Actual cost
Actual time
Location of project files
Scope of the study:
The company wants to track information on 20 past and current projects and wants the database to be able to handle 100 projects total. The required fields to be captured and metrics to be monitored from each segment includes main responbile people ( projectmanger, sponsor information),timeline of project, cost associated with it ( actual budget, completion time cost),time involved in completion of project.The files of project has to be systematically placed in folders and proper markers has to be given.