Question

Write a scope statement based on the information below: Analysis Design Implementation Collect list of 20...

Write a scope statement based on the information below:

Analysis

Design

Implementation

Collect list of 20 projects

Gather detailed requirements for desired outputs from the database

Enter project data

Gather information on projects

Create fully attributed, normalized data model

Test database

Define draft requirements

Create list of edit rules for fields, determine default values, develop queries, and determine formats for reports

Make adjustments, as needed

Create entity relationship diagram for database

Develop list of queries required for database

Conduct user testing

Create sample entry screen

Review design information with customer

Make adjustments based on user testing

Create sample report

Make adjustments to design based on customer feedback

Create online Help, user manual, and other documentation

Develop simple prototype of database

Create full table structure in database prototype

Train users on the system

Review prototype with customer

Create data input screens

Make adjustments based on customer feedback

Write queries

Create reports

Create main screen

Review new prototype with customer

The activities and tasks defined in the project plan must be undertaken within the scope of the project. For this reason, reiterate the scope of the project here as defined in the Project Charter.

Background Info:

Exercise A-4: Project Tracking Database

Expand the Project Tracking Database example. Assume that XYZ Company wants to create a history of project information, and the Project Tracking Database example is the best format for this type of history. The company wants to track information on 20 past and current projects and wants the database to be able to handle 100 projects total. The company wants to track the following project information:

Project name

Sponsor name

Sponsor department

Type of project

Project description

Project manager

Team members

Date project was proposed

Date project was approved or denied

Initial cost estimate

Initial time estimate

Dates of milestones (e.g., project approval, funding approval, project completion)

Actual cost

Actual time

Location of project files

Homework Answers

Answer #1

Scope of the study:

The company wants to track information on 20 past and current projects and wants the database to be able to handle 100 projects total. The required fields to be captured and metrics to be monitored from each segment includes main responbile people ( projectmanger, sponsor information),timeline of project, cost associated with it ( actual budget, completion time cost),time involved in completion of project.The files of project has to be systematically placed in folders and proper markers has to be given.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
UPS COMPETES GLOBALLY WITH INFORMATION TECHNOLOGY United Parcel Service (UPS) started out in 1907 in a...
UPS COMPETES GLOBALLY WITH INFORMATION TECHNOLOGY United Parcel Service (UPS) started out in 1907 in a closet-sized basement office. Jim Casey and Claude Ryan—two teenagers from Seattle with two bicycles and one phone—promised the “best service and lowest rates.” UPS has used this formula successfully for more than a century to become the world’s largest ground and air package-delivery company. It’s a global enterprise with nearly 400,000 employees, 96,000 vehicles, and the world’s ninth largest airline. Today UPS delivers 16.3...
CASE 3.2 Horizon Consulting Patti Smith looked up at the bright blue Carolina sky before she...
CASE 3.2 Horizon Consulting Patti Smith looked up at the bright blue Carolina sky before she entered the offices of Horizon Consulting. Today was Friday, which meant she needed to prepare for the weekly status report meeting. Horizon Consulting is a custom software development company that offers fully integrated mobile application services for iPhonetm, Androidtm, Windows Mobile® and BlackBerry® platforms. Horizon was founded by James Thrasher, a former marketing executive, who quickly saw the potential for digital marketing via smartphones....
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
The Halls Gap Wildlife Park offers a unique Australian wildlife experience. The park offers a scenic...
The Halls Gap Wildlife Park offers a unique Australian wildlife experience. The park offers a scenic comfortable nature walk around the facilities, with the chance to get up close and personal to some of Australia’s most famous native animals. With over 100 kangaroos roaming free, around the park, there is an opportunity to experience hand feeding these amazing animals. Visitors also have a chance to interact with koalas, wombats, and a variety of reptiles ranging from snakes to lizards and...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
Analysis: This section should include the issue register as a bare minimum, but may include also...
Analysis: This section should include the issue register as a bare minimum, but may include also why-why diagrams, a Pareto chart, a waste table and/or value-added analysis table. Flow analysis or simulation of this case study might be possible but might require making a lot of assumptions given the provided data. The first part of the project: Introduction    Walmart has continued to retain the top position on the Fortune 500 list for a consecutive fifth year. The brand has...
Item 1 In the case below, the original source material is given along with a sample...
Item 1 In the case below, the original source material is given along with a sample of student work. Determine the type of plagiarism by clicking the appropriate radio button. Original Source Material Student Version A communication channel is the means by which messages get from one individual to another. The nature of the information-exchange relationship between a pair of individuals determines the conditions under which a source will or will not transmit the innovation to the receiver and the...