The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown in the order in which they were received.
Job |
Processing Time (hrs) |
Due (hrs from now) |
W |
4 |
4 |
X |
3 |
5 |
Y |
2 |
2 |
Z |
1 |
1 |
If he or she uses the earliest due date first priority rule to schedule these jobs, what will be the average tardiness?
The o.wner/operator of t.he local fra.nchise of Ha.ndyman, Inc. has 4 jobs to complete today, shown in the order in which they were received.
Job |
Processing Time (hrs) |
Due (hrs from now) |
W |
4 |
4 |
X |
3 |
5 |
Y |
2 |
2 |
Z |
1 |
1 |
If he or she uses the earliest due date first priority rule to schedule these jobs, what will be the average tardiness.
Answer -According to the table the average tardiness would be 2 hours.