The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown...

The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown in the order in which they were received.

Job

Processing Time (hrs)

Due (hrs from now)

W

4

4

X

3

5

Y

2

2

Z

1

1

If he or she uses the earliest due date first priority rule to schedule these jobs, what will be the average tardiness?

Homework Answers

Answer #1

The o.wner/operator of t.he local fra.nchise of Ha.ndyman, Inc. has 4 jobs to complete today, shown in the order in which they were received.

Job

Processing Time (hrs)

Due (hrs from now)

W

4

4

X

3

5

Y

2

2

Z

1

1

If he or she uses the earliest due date first priority rule to schedule these jobs, what will be the average tardiness.

Answer -According to the table the average tardiness would be 2 hours.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Processing Due Job Time (days) Date (Days) W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A. 0 B. 1 C. 2 D. 3 E. 4
You have the following information on four jobs. Today is the beginning of day 1, so...
You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining. Job Time Needed (days) Due (days) P 8 8 Q 10 23 R 3 17 S 6 30 T 4 29 U 7 24 1. If you order these jobs by Shortest Process Time rule, the order will be: 2. If you order these jobs by Earliest Due...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
Develop a 2018 individual tax return (with all required forms and supporting schedules) for Rob and...
Develop a 2018 individual tax return (with all required forms and supporting schedules) for Rob and Laura Petrie that is both professional in appearance and technically correct. The use of tax software or a professional tax preparer to complete this project is prohibited. You can access fill-in forms (in pdf format) on the IRS website (www.irs.gov) by clicking on “More” on the left side of the homepage in the “Forms and Pubs” section. Next, click on the “Current Forms and...
Please read the article and answear about questions. Determining the Value of the Business After you...
Please read the article and answear about questions. Determining the Value of the Business After you have completed a thorough and exacting investigation, you need to analyze all the infor- mation you have gathered. This is the time to consult with your business, financial, and legal advis- ers to arrive at an estimate of the value of the business. Outside advisers are impartial and are more likely to see the bad things about the business than are you. You should...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT