Question

Problem 12-3 The following table lists the components needed to assemble an end item, lead times...

Problem 12-3

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

Item Lead Time Amount
on Hand
Direct Components
End 3 0 L(2), C(1), K(3)
L 3 9 B(2), J(3)
C 4 14 G(2), B(2)
K 4 19 H(4), B(2)
B 3 27
J 4 32
G 4 5
H 2 0


a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)

Additional units             

b. An order for the end item is scheduled to be shipped at the start of week 15. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)

The latest week            

Homework Answers

Answer #1

(a) To assemble end item, 2 units of L, 1 unit of C, and 3 units of K are required.

To assemle L, c, and L, 2 units of B in each are required.

Hence to assemle an end item, Total B units required = (2*2) + (1*2) + (3*2) = 12 units of B for 1 end item

Total B units to assemble 43 end item = 43 * 12 = 516 units

Available inventory of B = 27 units

Additional units of B required = 489 units

(b) To complete an end item, inventory required are 12 units of H, 12 units of B, 2 units of G, 6 units of J.

All these inventories are already available in stock except for H. H item has a lead time of 2 weeks, hence order can be started from the start of week 13, and H will be delivered in week 15 and all items can be assembled and shippeed in the start of week 15.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item lead time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 5 Eighty units of end item E are needed at the beginning of week 6....
Problem 5 Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J now on hand. Lead times...
The following table lists the components used in assembling item FG-A. The following information is also...
The following table lists the components used in assembling item FG-A. The following information is also included for each component: lead time, the on-hand supply, and direct components. Item Lead Time (days) Available Inventory Direct Components FG-A 1 0 SA-B(1), SA-C (2), SA-D(2) SA-B 1 0 SA-D(2) SA-C 2 0 E (1), F(2) SA-D 2 0 E(3) E 1 10 --- F 3 5 --- Construct a product structure tree at a lowest level coding. Prepare a time-phased product structure....
Consider an item by the name of Z which has components 2X’s and one Y. Gross...
Consider an item by the name of Z which has components 2X’s and one Y. Gross Requirements for Z are 0, 35, 55, 60 respectively. The inventory status of each as well as lead times is as below. Find the 4 week MRP schedule for all components.                               On Hand              Lot Size                Lead Time Z                            100                        LFL                    1 X                               20                     100 +                  1 Y                               10                     150+                   1                                a. What is the On Hand Inventory of Z...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 57 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
Product A is made from components B and C. Item​ B, in​ turn, is made from...
Product A is made from components B and C. Item​ B, in​ turn, is made from D and E. Item C also is an intermediate​ item, made from F and H.​ Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead​ times: Item A B C D E F G H Lead Time​ (weeks) 1 1 2 2 6 4 4 6 a. What lead time​ (in weeks)...
An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25,...
An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25, 25, 0, 40, 0, and 50 units. The current on-hand inventory is 80 units. The order policy is to produce in lots of 100. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 9, 0, 0, 5, 3, 7, and 0 units. At present, no MPS quantities are on-hand for this item. The lead time is 2 weeks....
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 10 15 45 10 30 90 20 45 160 Use the least total cost lot-sizing method to determine the quantity to order with...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 85 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 55 10 22 70 87 19 63 210 58 Use the least total cost and the least unit cost lot-sizing methods to determine...