Question

Describe the process of manually crashing a project network.

Describe the process of manually crashing a project network.

Homework Answers

Answer #1

Crashing of a project network means shortening the project duration by reducing the time of one of the critical project activity to less than it's normal activity time. Project crashing is directly related to cost. Since, the duration is to be reduced, more expenditures are nade on labour and other resources hence the cost increases. Hence, they crashing and cost has a inverse relationship.

However, process of manual crashing of a project network is cumbersome.it is basically a trial and error approach useful for demonstrating the process of crashing. In larger networks, it often becomes unmanageable with more than one critical network/activity. As we try to crash one critical network by some units, the other network needs to be reduced too. Hence, the whole crashing process becomes a lot of work.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Describe the process of manually crashing a project network.
Describe the process of manually crashing a project network.
What is project crashing?
What is project crashing?
What is the term used for shortening a logic network after construction has begun? Crashing Fast...
What is the term used for shortening a logic network after construction has begun? Crashing Fast tracking Resource leveling Time-scaled network How is free-float defined? The amount of slack between activities The amount of slack within a path of activities The amount of slack accumulated throughout the logic network The amount of slack in a node The path with the longest sequence of activities in a project plan is called: Crises Critical Concrete Detailed        Lead-times are used to determine...
What is the crashing techniques used for? a. Activity sequencing b. Cost reduction c. Network diagramming...
What is the crashing techniques used for? a. Activity sequencing b. Cost reduction c. Network diagramming d. Duration compression
The process where we shorten the duration of a project in the cheapest manner possible. a....
The process where we shorten the duration of a project in the cheapest manner possible. a. Project minimization b. Project crashing c. Project leaking d. Project alignment
In “crashing” a project, a manager will generally focus on activities which: are NOT on the...
In “crashing” a project, a manager will generally focus on activities which: are NOT on the critical path are the least costly to crash are costly to crash and are on the critical path are on the critical path and are the least costly to crash are the easiest to crash
CPM a. is a network technique that allows three time estimates for each activity in a...
CPM a. is a network technique that allows three time estimates for each activity in a project. b. assumes we do not know ahead of time what activities must be completed. c. assumes that activity time estimates follow the normal probability distribution. d. is a deterministic network technique that allows for project crashing.
Define Scope is the process of developing the: ​ a. project scope management plan. b. project...
Define Scope is the process of developing the: ​ a. project scope management plan. b. project scope network diagram. c. detailed specifications of the project outcomes and products. d. project work breakdown structure.
) As a project manager, describe FIVE (5) reasons why assessing the process-based quality is one...
) As a project manager, describe FIVE (5) reasons why assessing the process-based quality is one of the crucial tasks to be carried out along the project management. (
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT