A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the task of attaching a watch to a wristband. In a preliminary study, he observed one of his workers perform this task five times, with the following results:
Observation | 1 | 2 | 3 | 4 | 5 |
Time (secs) | 29 | 23 | 31 | 37 | 26 |
What is the standard time for this task if the employee worked at a 9 percent slower pace than average, and an allowance of 23 percent of the workday is used?
(Keep two decimal places in your answer)
Average observed time = ( 29 + 23 + 31 + 37 + 26) / 5 = 29.2 secs
Performance rating factor = 91 % ( since it is mentioned that workers work at a 9 percent slower place )
Therefore ,
Normal time = Performance rating factor (%) / 100 x Average observed time = 0.91 x 29.2 = 26.57 seconds
Given,
Allowance factor = 23 percent
Therefore , Standard time = ( 1 + allowance factor/100) x Normal time = 1.23 x 26.57 seconds = 32.68 seconds
STANDARD TIME FOR THIS TASK = 32.68 SECONDS |