Question

Sch.W Foundry, a metalwork plant in Quebec, has just decided to make a major investment in...

Sch.W Foundry, a metalwork plant in Quebec, has just decided to make a major investment in new air pollution control equipment. The plant, however, must be shut during this installation process. Sch.W’s board of directors estimates that the company can survive no more than 16 weeks without production in full swing. The managing partner wants to make sure the installation of the filtering system progresses smoothly and on time.

The activities involved in the foundry project are presented in the table below. Find the earliest start and finish, latest start and finish, and slack of each activity. Which activities are critical? Will the project finish in 16 weeks?

Activity

Description

Time Estimate (weeks)

Immediate Predecessor(s)

A

Building internal components

3

-

B

Modify roof and floor

4

-

C

Construct collection stack

3

A

D

Pour concrete and install frame

5

B

E

Build high-temperature burner

5

C

F

Install control system

3

C

G

Install air pollution device

5

D,E

H

Inspection and testing

3

F,G

Homework Answers

Answer #1

Please refer the image uploaded.

ES = Early start, LS = Latest start , EF = Early Finish, LF = Latest Finish

Slack Formula = LS - ES

ES , EF , LS , LF , Slack (activity A) = 0 week, 3 weeks, 0 weeks , 3 weeks, 0 week (Critical activity as Slack = 0)

ES , EF , LS , LF , Slack (activity B) = 0 week, 4 weeks, 2 weeks , 6 weeks, 2 weeks

ES , EF , LS , LF , Slack (activity C) = 3 week, 6 weeks, 3 weeks , 6 weeks, 0 week (Critical activity as Slack = 0)

ES , EF , LS , LF , Slack (activity D) = 4 week, 9 weeks, 6 weeks , 11 weeks, 2 weeks

ES , EF , LS , LF , Slack (activity E) = 6 week, 11 weeks, 6 weeks , 11 weeks, 0 week (Critical activity as Slack = 0)

ES , EF , LS , LF , Slack (activity F) = 6 week, 9 weeks, 13 weeks , 16 weeks, 7 weeks

ES , EF , LS , LF , Slack (activity G) = 11 week, 16 weeks, 11 weeks , 16 weeks, 0 week (Critical activity as Slack = 0)

ES , EF , LS , LF , Slack (activity H) = 16 week, 19 weeks, 16 weeks , 19 weeks, 0 week (Critical activity as Slack = 0)

A - C - E - G - H (Critical path)

No, the project will not finish in 16 weeks but it will take 19 weeks to finish (Answer)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs — 13 8 30 130 B Order equipment A 9 6 120...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
A car dealership decided to add an annex to its sales office as a customer lounge....
A car dealership decided to add an annex to its sales office as a customer lounge. The project is divided into the activities listed in the following table. The immediate predecessor(s), times and costs, both normal and crashed, are given. To finish the project sooner, the dealership has to make time and cost tradeoffs. If the project needs to be finished in 25 weeks, you are required to formulate a linear programming model to decide about how much to crash...
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine...
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine activities involved. These activities have been labeled A through I in the following table. The company is planning to finish the project in 34 weeks. Please answer the following questions. Determine the expected (estimated) duration and variance for each activity. You can round the expected duration numbers without decimals. Activity Immediate Predecessor(s) Optimistic Probable Pessimistic Expected duration Variance A -- 5 9 13 Answer...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss of sales and disruption of customer shopping habits, Mega Mart wants to complete this renovation without closing the store itself, by temporarily co-locating goods from one area of the store into another, creating open spaces for renovation and re-occupation. Mega Mart is divided into four basic areas of goods: Clothing, Electronics, House Wares and Foodstuffs. Each of these areas will need to be temporarily...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to turn a major coal fired generating station project around. Currently at 36 percent construction completion, the project is shifting from an emphasis on civil and structural work to bulk production. Cooperation of the owner, the multi-prime contractors, and strong labor unions is cach vital for performance improvement. The analysis of this project involves: 1) identification of significant external influences on the project organization, 2)...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...